22 facts from the tender

Ministry of Railways published this works tender on eProcure on 10 Oct 2026, for Ghazipur, Uttar Pradesh. The estimated value is ₹6.4 Cr and the EMD is ₹12.9 L. It closes on 2 Nov 2026, 12:30 pm IST. Tender ID 92618555 · Ref SG-DSE-ST-02-26.

Timeline

  1. Published10 Oct 2026 · 1:40 pm
  2. Closes2 Nov 2026 · 12:30 pm

Bidding

Bid type
Single
Contract type
Works - General · Expenditure
Tender type
Single
Tendering section
MGS
Bidding system
Single Packet System
Bidding style
Single Rate for Each Schedule Item
Validity of offer
60 days
Completion period
24 Months
Tender document cost
None
JV / consortium
Not allowed
Ranking order
Lowest to Highest
Expenditure type
Revenue
Pre-bid meeting
None

Buyer

Inviting authority
DDU DIVISION-S AND T/EAST CENTRAL RLY
Organisation type
Central Govt. Ministry/Department
Product category
Railway related Products
Location
Ghazipur, Uttar Pradesh
Portal
eProcure
Inviting officer
Sr. DSTE/ECR/MGSDDU DIVISION-S AND T/EAST CENTRAL RLY

Important dates

Published
10 Oct 2026, 1:40 pm IST
Bidding starts
19 Oct 2026
Closes
2 Nov 2026, 12:30 pm IST

Declarations by the buyer

  • Complies with the Public Procurement (Make in India) Order 2017
  • The tender inviting authority confirms this tender does not violate the GFR rules on procurement through GeM
  • Bidders from a country sharing a land border with India must be registered with the competent authority

Schedule of work

3 items
ItemQuantityRailways’ estimated rateAmount
Schedule 1 · Comprehensive Annual Maintenance Contract of Siemens make Electronic Interlocking of DDU Division for 02 years.
1Comprehensive Annual Maintenance Contract (AMC) for Siemens make Electronic Interlocking (EI) system installed at Karwandiya - Pahleza Block Section ALH-1 at LC37 , Sasaram - Karwandiya Block Section ALH-1 at LC40 , Sasaram - Karwandiya Block Section ALH-2 at LC41 , Manpur-Bandhua: ALH-1 at LC67 , Dehri On Sone , Manpur , Son Nagar(RRI) , Chandauli Majhwar - Saidraja Block Section ALH-17 , Chandauli Majhwar - Saidraja Block Section ALH-18 , Ganjkhawja - Chandauli Majhwar Block Section ALH-19 , Ganjkhawja - Chandauli Majhwar Block Section ALH-20 of DDU Division of East Central Railways for period of 2 years.130 Month₹79,016.34₹1,02,72,124.20
2Comprehensive Annual Maintenance Contract (AMC) for Siemens make Electronic Interlocking (EI) system installed at BaghoiKusa , Chiraila Pauthu , Jakhim , Flyover Cabin DDU, Flyover Cabin (Sonenagar) , IMGE , DGO, Mohamdganj , Saiyadraja , Untari Road , Chandauli Majhwar , Kosiyara , Karkatta , Satbahini , Sisigi, Ankorah , Haider Nagar , Kajrat Nawadih ,Nabinagar Road , Karwandia of DDU Division of East Central Railways for period of 2 years. (UP TO 100 Routes)418 Month₹79,016.34₹3,30,28,830.12
3Comprehensive Annual Maintenance Contract (AMC) for Siemens make Electronic Interlocking (EI) system installed at Japla, Bhabhua Road , Pahleja , Ganjkhwaja , Barkisaliya , Sasaram , Baghabisunpur of DDU Division of East Central Railways for period of 2 years. (Above 100 Routes)168 Month₹1,25,064.66₹2,10,10,862.88
Total₹6,43,11,817.20

Bids quote a rate in rupees for each item · The total matches the advertised value.

Documents

22 files

Documents to submit

Commercial-Compliance

  • Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.

    Document optional
  • Verification of Tender's credentials The tenderers shall submit a copy of certificate stating that they are not liable to be disqualified and all their statements/documents submitted along with bid are true and factual. Standard format of the certificate to be submitted by the bidder is enclosed as Annexure-V. Non submission of a copy of certificate by the bidder shall result in summarily rejection of his/their bid. It shall be mandatorily incumbent upon the tenderer to identify, state and submit the supporting documents duly self attested / digitally signed by which they/he are/is qualifying the Qualifying Criteria mentioned in the Tender Document.

    Document required
  • If it is NOT mentioned in the submitted tender that tender is being submitted on behalf of a Sole Proprietorship firm / Partnership firm / Joint Venture / Registered Company etc., then the tender shall be treated as having been submitted by the individual who has signed the tender. The tenderer whether sole proprietor / a company or a partnership firm / joint venture (JV) / registered society / registered trust / HUF / LLP etc if they want to act through agent or individual partner(s), should submit along with the tender, a copy of power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, specifically authorizing him/them to sign the tender, submit the tender and further to deal with the Tender/ Contract up to the stage of signing the agreement except in case where such specific person is authorized for above purposes through a provision made in the partnership deed / Memorandum of Understanding / Article of Association /Board resolution, failing which tender shall be summarily rejected.

    Document required
  • A separate power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, shall be submitted after award of work, specifically authorizing him/them to deal with all other contractual activities subsequent to signing of agreement, if required. Note: A Power of Attorney executed and issued overseas, the document will also have to be legalized by the Indian Embassy and notarized in the jurisdiction where the Power of Attorney is being issued. However, the Power of Attorney provided by Bidders from countries that have signed the Hague Legislation Convention 1961 are not required to be legalized by the Indian Embassy if it carries a conforming Appostille certificate.

    Document optional
  • Following documents shall be submitted by the tenderer in case of Sole Proprietorship Firm: Sole Proprietorship Firm:

    1. An undertaking that he is not blacklisted or debarred by Railways or any other Ministry / Department of Govt. of India from participation in tender on the date of opening of bids, either in individual capacity or as a member of the partnership firm or JV in which he was / is a partner/member.
    2. All other documents in terms of explanatory notes in clause 10 of GCC 2022.
    Document required
  • Following documents shall be submitted by the tenderer in case of HUF: A copy of notarized affidavit on Stamp Paper declaring that his Concern is a proprietary Concern and he is sole proprietor of the Concern OR he who is signing the affidavit on behalf of HUF is in the position of 'Karta' of Hindu Undivided Family (HUF) and he has the authority, power and consent given by other members to act on behalf of HUF.

    1. An undertaking that the HUF is not blacklisted or debarred by Railways or any other Ministry / Department of Govt. of India from participation in tender on the date of opening of bids, either in individual capacity or as a member of the partnership firm or JV in which HUF was / is a partner/member.
    2. All other documents in terms of explanatory notes in clause 10 of GCC 2022. Following documents shall be submitted by the tenderer in case of Partnership Firm: The tenderer shall clearly specify that the tender is submitted on behalf of a partnership firm.
      1. A notarized copy of partnership deed.
      2. A notarized or registered copy of Power of Attorney in favour of the individual to tender for the work, sign the agreement etc. and create liability against the firm. Note :- One or more of the partners of the firm or any other person (s) shall be designated as the authorized person (s) on behalf of the firm, who will be authorized by all the partners to act on behalf of the firm through a "Power of Attorney", specially authorizing him / them to submit & sign the tender, sign the agreement, receive payment, witness measurements, sign measurement books, make correspondences, compromise / settle / relinquish any claim (s) preferred by the firm, sign "No Claim Certificate", refer all or any dispute to arbitration and to take similar such action in respect of the "said tender" / contract. Such "Power of Attorney" shall be notarized / registered and submitted along with the tender.
    Document required
Show all 14
  • Following documents shall be submitted by the tenderer in case of Company registered under Companies Act 2013:

    1. The copies of MOA (Memorandum of Association) / AOA (Articles of Association) of the company
    2. A copy of Certificate of Incorporation
    3. A copy of Authorization/Power of Attorney issued by the Company (backed by the resolution of Board of Directors) in favour of the individual to sign the tender on behalf of the company and create liability against the company.
    4. An undertaking that the Company is not blacklisted or debarred by Railways or any other Ministry / Department of Govt. of India from participation in tender on the date of opening of bids, either in individual capacity or as a member of the partnership firm or JV in which the Company was / is a partner/member.
    Document required
  • Following documents shall be submitted by the tenderer in case of LLP (Limited Liability Partnership): If the tender is submitted on behalf of a LLP registered under LLP Act-2008, the tenderer shall submit along with the tender: A copy of LLP Agreement.

    1. A copy of Certificate of Incorporation
    2. A copy of Power of Attorney/Authorization issued by the LLP in favour of the individual to sign the tender on behalf of the LLP and create liability against the LLP.
    3. An undertaking by all partners of the LLP that they are not blacklisted or debarred by Railways or any other Ministry / Department of the Govt. of India from participation in tenders / contracts as on the date of submission of bids, either in their individual capacity or in any firm/LLP or JV in which they were / are partners/members. Concealment / wrong information in regard to above shall make the contract liable for determination under Clause 62 of the Standard General Conditions of Contract.
    4. All other documents in terms of Para 10 of the Tender Form (Second Sheet).
    Document required
  • The Railway reserves the right to verify all statements, information and documents submitted by the bidder in his tender offer, and the bidder shall, when so required by the Railway, make available all such information, evidence and documents as may be necessary for such verification. Any such verification or lack of such verification, by the Railway shall not relieve the bidder of its obligations or liabilities hereunder nor will it affect any rights of the Railway there under.

    Document optional
  • In case of any information submitted by tenderer is found to be false forged or incorrect at any time during process for evaluation of tenders, it shall lead to forfeiture of the tender Earnest Money Deposit besides banning of business for a period of upto five years. In case of any information submitted by tenderer is found to be false forged or incorrect after the award of contract, the contract shall be terminated. Earnest Money Deposit (EMD), Performance Guarantee and Security Deposit available with the railway shall be forfeited. In addition, other dues of the contractor, if any, under this contract shall be forfeited and agency shall be banned for doing business for a period of upto five years.

    Document optional
  • Certificates and testimonials regarding contracting experience for the type of job for which tender is invited with list of works carried out in the past.

    Document required
  • Non-compliance with any of the conditions set forth therein above is liable to result in the tender being rejected.

    Document required
  • Certificates which may be an attested Certificate from the client, Audited Balance Sheet duly certified by the Chartered Accountant etc regarding contractual payments received in the past.

    Document required
  • The list of personnel / organization on hand and proposed to be engaged for the tendered work. Similarly list of Plant & Machinery available on hand and proposed to be inducted and hired for the tendered work.

    Document required

The tenderer shall clearly specify whether the tender is submitted on his own (Proprietary Firm) or on behalf of a Partnership Firm / Company / Joint Venture (JV) / Registered Society / Registered Trust / Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc.

The tenderer(s) shall enclose the attested copies of the constitution of their concern, and copy of PAN Card along with their tender.

Tender Documents in such cases are to be signed by such persons as may be legally competent to sign them on behalf of the firm, company, association, trust or society, as the case may be.

Concealment / wrong information in regard to above shall make the contract liable for determination under Clause 62 of the General Conditions of Contract.

(v) All other documents in terms of explanatory notes in clause 10 of GCC 2022

Eligibility

Standard Financial Criteria

  • The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.

    Document required

Special Technical Criteria

  • The Firm should be OEM or Authorized dealer of OEM for the manufacturing, commissioning, servicing and maintenance of Siemens make E.I.

    Document required

Standard Technical Criteria

  • The Tenderer must have successfully completed or substantially completed any of the following during last 7(Seven) years , ending last day of month previous to the one in which tender is invited:

    1. Three similar works costing not less than the amount equal to 30% of advertised value of the tender, or
    2. Two similar works costing not less than the amount equal to 40% of advertised value of the tender, or
    3. One similar work costing not less than the amount equal to 60% of advertised value of the tender. NOTE :- Work experience certificate from private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organisation, work experience certificate issued by Public listed company having average annual turnover of Rs 500 crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/ registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate has been issued by a person authorized by the Public listed company to issue such certificates. In case tenderer submits work experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details of payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate.
    Document required

Partnership firm/Joint Venture (JV) / Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc.

  • Please submit a certificate in the prescribed format (please download the format from the link given below). Non submission of the certificate, or submission of certificate either not properly filled in, or in a format other than the prescribed format shall lead to summary rejection of your offer. ( Click here to download the Format of Self Certification)

Check each criterion against the tender notice before you bid.

Commercial conditions

EMD
₹1,286,200
Tender fee
None

Terms & conditions

57 conditions

General Instructions

  • GCC -2022 with latest amendments and instructions is an integral part of the contract document. All terms and conditions mentioned therein to be followed.

  • Rates are inclusive of all taxes/octroi, license fee, royalty charges etc. legally leviable by State, Central Govt. and/or any other local authority.

  • In addition to GCC 2022 and Indian Railway Unfiled standard specification works materials volume I II 2010, revised up to date, special condition attached shall also apply.

  • Taxes as per GST (1st july2017), Income tax, TDS, Sales tax/Business tax, Royalty etc Royalty etc. will be recovered as per extant instruction on the subject.

  • Eligibility criteria for works tender in respect of partnership firms to be dealt as per GCC -2022.

  • In case the tenderer is a partnership firm s , the experience, solvency and turn over shall be in the name and style of the firm only.

  • If the tenderer is a partnership firm, all the partners shall be jointly and severally liable for successful completion of the work and no request for change on the certification of the firm shall be entertained.

  • During the currency of the contract, no partner of the firm shall be permitted to withdraw from partnership business and in such and event it shall be treated as breach of trust and abandonment of the contract.

  • Any Conditional offer will be summarily rejected.

  • For Standard Financial criteria and Standard Technical criteria - Tenderers are required to submitted authenticated certificate along with the tenders from officers of government or semi- government/public sector undertakings under whom the work has been executed indicating there in the name of work executed, value of works/payment details and period during which completed. Such certificates should have signature and seal of the concerned officer. In the absence of such certificate the tender may not be considered.

Show all 56
  • BOOKS OF REFERENCE These tender documents are to be read with the followings books with versions updated/corrected/modified up to the date of tender opening:

    1. Standard General Conditions of Contract 2022 as amended by updated correction slips termed GCC 2022.
    2. Eastern Railway L&M Sch 87 as amended by updated correction slips.
    3. Railway Engineering department unified standard schedule or rates 2012 as amended by updated correction slips (termed USSOR, 2012) up to the date of tender dropping.
    4. Standard specifications contained in Indian Railways Hand Book Specifications (works and materials)2010. These four books are where-in-after called the "Books of reference" and shall govern this tender as well as the contract resulting from the acceptance from this tender, to the extent that these contents do not conflict with the contains of the various chapters of these documents.
  • For those conditions for which standard formats have been given in the uploaded document titled-Formats for uploading of various format. The information should only be submitted in these standard formats.

  • Railway administration will not be responsible for any delay/difficulties/inaccessibility of the downloading facility for any reason whatsoever. In case of any discrepancy between the tender document downloaded from the internet and the master copy available in the office mentioned above, later shall prevail and will be binding on the tenderer. No claim on this account will be entertained.

  • If working through contract Labour, the contractor must register with Labour Commissioner necessary license to be submitted with tender or to be produced before signing of contract agreement.

  • The contractor will be permitted to make use of the serviceroads already existing within the Railway possession. Ifadditional service roads are required within Railway premisesthe contractor may be allowed to make them at his own costwith the prior approval of the Railway's Engineer. All serviceroads required outside Railway boundary shall be constructed by the contractor at his own risk and cost. These roads shall be maintained by the contractor at his own cost. The Railway reserves the right to make use of these service roads as andwhen necessary without any payment to the contractor.

  • The Tenderer/Contractor may be required to engage surplus/retrenched casual labours of the Railway, if found suitable upto the extent as deemed fit by the Railway during the currencyof the contract. The terms of employment between suchlabour and the Tenderer/Contractor may be on mutuallyagreed terms subject to the statutory provisions contained in the Labour Regulations and enactments. The Contractor shall indentify the Railway against any claim arising out of employment of such labour and the Railway shall not be party to any disputes etc. arising out of the employment of such labour by the Tenderer/Contractor.

  • The intending tenderer should study with General Conditions of Contract, Special Conditions of Contract, and Instructions to Tenderer, Technical Specification, Drawings, Documents, Schedules etc. enclosed and also the General Conditions of Contract, 2022 of the Engg. Department with up to date modifications and IRS Conditions of Contract for the Stores department with up to date modifications all herein after collectively referred to as Tender Specification.

  • Provision in the instructions, General Conditions of Contract and Special Conditions of the Contract in the tender documents will override any overlapping provisions of General Conditions of contract 2022 of the Engg with up to date modifications and IRS Conditions of Contract for the Stores department with up to date modifications. When there is conflict between General Conditions of contract 2022 and special conditions of the contract, the special conditions shall prevail.

  • Other Local Taxes levied either by Governmental agency or by Municipal agency shall not be paid by the Railway. These are deemed to be included in the F.O.R. price, unless specifically brought out in the offer.

  • SCHEDULE COVERING DELIVERY OF MATERIALS AND THE EXECUTION OF THE WORK AT SITE: The tenderer shall attach to his offer a time schedule showing the guaranteed time

    1. schedule for the supply of materials, the progress and completion of the works at site.
    2. The time Schedule shall be as referred to in Para - 4 of Instruction to tenderer.
    3. The tenderer should offer the time schedule for supply of materials, the duration of erection and completion period for the work and it should be kept the barest minimum. This aspect will be particularly taken into account while examining the offer. In any case this period shall not be more than the time specified in the tender documents, reckoning from the of date of issue of Letter of Acceptance.
  • GENERAL REQUIREMENT :

    1. All documents to be submitted in connection with this tender will be written in English.
    2. Dimensions, weights etc. shall be in Metric System/British Standard Equivalents. The technical terms and symbols to be used will be as per General and Subsidiary Rules/Signal Engineering Manual/Extant Practice of East Central Railway.
  • ADVICE OF CANCELLATION OF DOCUMENTS BY TENDERER :The Cancellation of any document such as Power of Attorney/Partnership deed etc. should be forthwith communicated by the contractor to the Rly. Administration in writing failing which the Rly. Administration shall have no responsibility or liability for an action taken on the strength of the said document.

  • Any individuals signing the tender or other documents Connected there with should specify whether he is signing :

    1. As sole proprietor of the concern or his attorney.
    2. As partner or Partners of the Firm.
    3. For the Firm per procure, or as a Director, Manager or Secretary in the case of a Limited Company.
  • THE RAILWAY NOT BOUND TO ACCEPT ANY TENDER The Railway shall not be bound to accept the Lowest or any Tender or to assign any reason for non-acceptance or rejection of a Tender. No Tender shall be deemed to have been accepted unless such acceptance shall have been notified in writing to the successful tenderer by the Railway. The Railway reserves the right to accept any tender in respect of the whole or any portion of the work specified in the tender or to divide or reduce the work or to accept any tender for less than the tendered quantity without assigning any reason whatsoever.

  • The General Instructions and Special Instructions mentioned in various para to be read in conjunction with uploaded tender document which contains important formats/Annexures and Technical bindings and schedule of work etc.

  • Letter of credit as mode of payment in works tenders or service tenders is available. If is an option for the contractor to take payment from Railways through a letter of credit (LC) arrangement. The details letter of credit is as under:- Option for Letter of Credit

    1. In case tender opts for payment through LC, following shall be the procedure to deal release of payment through LC:
      1. The LC shall be a sight LC.
      2. The contractor shall select his Advising/Negotiating bank for LC. The incidental cost forward issue of LC and its operation thereof shall be borne by the contractor.
      3. SBI, New Delhi ,Main Branch will be the nodal branch for issue of LCs based on online requests received from Railway Accounts Units fortenders opened in financial year 2018-19. SBI branches where the respective Railway Accounts Office has its Account (local SBI branch) will be the issuance/reimbursing branch for LC issued under this arrangement. The Bank shall remain same for this tender till completion of contract. The incidental cost @ 0.15% per annum of LC value, towards issue of LC and operation thereof shall be borne by the contractor and shall be recovered from his bills.
      4. The LC shall be opened initially for duration of 180 to 365 days in consultation with contractor. The LC shall be extended time to time as per progress of the contract, on the request of the contractor. The value of LC to be opened initially as well as extended thereafter shall be finalized by the engineer in consultation with the contractor on the basis of expected progress of work.
      5. The LC terms and conditions shall inter-alia indemnify and save harmless the Railway from and against all losses, claims and demands of every nature and description brought or recovered against the Railways by reason of any act or omission of the contractor, his agents or employees, in relation to the Letter of Credit(LC). As sums payable/borne by Railways on this account shall be considered as reasonable compensation and paid by contractor.
      6. The LC terms and conditions shall inter-aliaprovided that Railways will issue a Document of Authorization (format enclosed as Annexure 2) after passing the bill for completed work, to enable contractor to claim the authorized amount from their bank.
      7. The acceptable, agreed upon document for payments to be released under the LC shall bethe Document of Authorization. Option for Letter of Credit
    2. In case tender opts for payment through LC, following shall be the procedure to deal release of payment through LC:
      1. The Document of Authorization shall be issued by Railway Accounts Office against each bill passerby Railways.
      2. On issuance of Document of Authorization, acopy of Document of Authorization shall be posted on IREPSfor download by the contractor. A digitally signed copy of Document of Authorization shall also be sent by Railway Account Officer to Railway's bank (Local SBI Branch).
      3. The contractor shall take print out of the Document of Authorization available on IREPS and present his claim to his bank (advisingBank) for necessary payments as per LC terms and conditions. The claim shall comprise of copy of Document of Authorization, Bill of Exchange and Bill.
      4. The payment against LC shall be subject to verification from Railway's Bank(Local SBI Branch).
      5. The contractor's bank (advising bank) shall submit the documents to the Railway's Bank (Local SBIBranch).
      6. The railway's bank (issuing bank) shall, after verifying the claim so r
  • For the service rendered by the RITES for inspection of materials supplied by the contractor in works contract, inspection charges @ 1% of the cost of materials including all taxes, excise duty etc. are to be borne by the contractor& no inspection charges are payable to RDSO by contractor for RDSO Inspected materials.

  • Provision of latest labour laws must be followed as per applicable.

Certificates from private individuals for whom such works are executed being executed is not acceptable.

Special Conditions

  • SCOPE OF WORK:The work is comprehensive Annual Maintenance Contract of Siemens make E.I. having :

    1. Preventive Maintenance: Provision of scheduled periodical maintenance visits (minimum one visit per Calendar month unless otherwise specified) to clean, test, adjust & checking up of all parameters for proper working of modules, parts & complete systems. This is mainly to prevent occurrence of failures. All the parameters to be recorded in a register with signature.
    2. Breakdown Maintenance: Repair/Replacement of defective cards/modules/sub-systems/parts/components in either in hardware or software or in any form. The repaired and replaced modules shall have same performance as that of original.
    3. Modification/upgradation of Hardware/Software as per policy guidelines issued from time to time by Railway Board/RDSO/HQ to overcome any deficiency noticed in the working of the system to improve reliability of the installation. As per RDSO/RB's guidelines will be done at the in commencement of AMC before passing of first on account bill and thereafter once in each year.
  • PERIOD OF CONTRACT The period of the contract will be for 02 (TWO) years from the date of issue of letter of Acceptance.

  • EXECUTION OF AMC -

    1. The contractor shall depute service engineers who are technically competent for maintenance of installations/rectification of failures, well conversant and fully equipped for all activities to be executed under the tender.
    2. The service engineers will be issued with valid identity card and competency certificate by the firm duly authorizing them to undertake the AMC work. Service engineers should be deployed at suitable locations (to be called service centers). Locations shall be selected in such a way that any failure reported shall be attended at the earliest. Maximum 05 locations will be under maintenance of one service engineer. Locations and their jurisdictions will be decided mutually by the firm and Sr. DSTE/DDU.
    3. These details of service engineers will be provided in their offer. The service engineers employed by OEM should be exclusive for the purpose of Annual Maintenance contract and should not be utilized for any other purpose such as installation/maintenance of other equipments/locations.
    4. Generally the service engineer will have weekly rest. However, he shall not move out of his section without permission of Sr. DSTE/DDU. In case he is required to go on leave or move outside his section, alternative arrangement for attending of breakdown/failures should be in place and intimated to Railway Administration before his leaving the section.
  • Execution of AMC - Addresses of the locations, Mobile Nos. & e- mail address shall be given to Railways for reporting of failures. Accordingly, failures will be reported by divisions at nominated locations. Contractor shall have a system of Call Registration at each of these locations. Once failure is reported at any of these locations, it should be acknowledged through allotment of a registration/reference No. This is important, as it will be required for future references. The firm's Engineer/Supervisor shall be available on telephone round the clock for passing on the information by Railways in case of failure.

  • Execution of AMC Contractor will be required to maintain sufficient spares for various cards/modules at each location. This is required for quick rectification. The service engineer will keep advised sectional ASTE/DSTE, SSE (Sig) and Signal Control of the DDU Division about his day to day movement. Inspection and maintenance should be carried out in presence of authorized representative of Sr. DSTE/DDU. Record of measurements of various parameters, their adjustments and replacement of modules/ cards/ equipments during the visit shall be maintained as per the Performa provided by Railways and shall be got counter signed by the Railway's representative during every visit at a station. Contractor shall maintain a register at each location for recording these details as per this Performa. A joint report of the same is to be submitted to the office of DRM(S&T) as per Performa.

  • Execution of AMC A separate register for details of attending failure/breakdown is to be maintained by the contractor at each station during the period of AMC. The details regarding the time of information received, failure/breakdown attended and its rectification, its nature material repaired/replaced and signature of the service Engineer and the authorized representative of Sr. DSTE/DDU should be recorded as per prescribed Performa Complete set of Tools required for maintenance must be available with service engineer during preventive maintenance/attending failure. If the service engineer feels that the failure is due to any other reason which is beyond this preview, the same should be reasonably supported by reports/measurements/readings etc. Railway decision in this regard shall be final.

  • In case Railway needs any guidance/training in modifying/enhancing the capacity of the system/minor shifting of the system, the contractor shall assist in completing this work and testing it.

  • Pre-site Inspection Before get into a maintenance contract the full working condition of E.I. system, (M/s Siemens make) should be jointly checked by firm's Authorized Engineer and JE/SSE (Signal) from division. If any servicing/replacement have to be undertaken for full functionality of the equipment, the same will be carried out at additional cost except the E.I system ( M/s Siemens make) which went defective during the currency of previous AMC.

  • Commencement of work:-The contract will be treated as valid from the date of issuance of the LAO.

  • Items Covered under AMC

    1. Complete EI equipment including all Module/components, accessories, VDU, hardware including peripherals equipments etc will be covered under AMC. One set means One EI. Any defective Module/components of the above said equipment is replaced by new one, old VDU/ Module/components will be taken by firm.
    2. EI yard viewer software, reloading of data base etc to support EI in failure analysis system.
  • Items not covered under AMC

    1. Servicing of Module/components of replacement of the same.
    2. Servicing of other make Module/components or replacement of the same
    3. The hardware changes or upgrades required due to change in signalling system or yard layout during AMC period will be carried out by the contractor on extra additional cost
  • Relocation of the equipments As this contract is only respect of present site of the equipment, for relocation of the equipment unless otherwise mutually agreed prior to relocating. However, this agreement does not cover charge for relocating the equipment and repairs or replacement if any, required because of relocation of the equipment.

  • Penalty Clause:

    1. For major Failure/ breakdown of the installation(resulting in disruption of railway traffic);-
      1. Total duration of failure/breakdown/non-functioning of the EI installation will be calculated every month (in no. of hours). Pro- rata rate of AMC per hour will be calculated and payment will be not be made for this downtime. Working Hours for the system shall be considered as 24 Hours per day. (Calculation shall be done as per details mentioned in Annexure A1).
      2. Further a penalty @ 50 times of the pro - rata of AMC charge per hour shall be levied for per hour downtime after a grace period of 2 hrs and up to 4 hrs after reporting failure/breakdown. (Calculation shall be done as per details mentioned in Annexure A2).(C) Further a penalty @ 100 times of the pro - rata of AMC charge per hour shall be levied for per hour downtime after 4 hours of reporting failure/breakdown till failure rectified (Calculation shall be done as per details mentioned in Annexure A3).
    2. For Minor Faults/Failures (which do not causes disruption in train traffic) of the installation: Penalty @ Rs. 500/- per failure per day or part thereof shall be levied for the minor faults/failure after a grace period of 24 hrs till failure is rectified. (Calculation shall be done as per details mentioned in Annexure B).Note: -
      1. Penalty can be reduced or waived if breakdown is on account of the railways.
      2. If minor faults/failures converts into major faults/failures after reporting, the downtime and penalty shall be governed vide para 1(a) & (b)
    3. For delayed scheduled preventive maintenance visit: A grace period of 05 days shall be allowed after which penalty @ 20% of Monthly AMC charge for per system per day of the installation may be levied for each passing day. (Details to be calculated as per Annexure-C. However, grace period will be zero for those ELECTRONIC INTERLOCKING SYSTEM equipment which has generated partial fault and does not lead to disruption of train traffic. (Calculation shall be done as per details mentioned in Annexure C).
  • Payment terms:

    1. Payment shall be made on monthly basis, after expiry of each month of satisfactory maintenance against bills to be submitted by the firm.Payment shall be made after maintenance service report, record of monthly visit, failure and servicing done or verified and satisfied by railway and required up time as specified is ensured.
    2. The following documents duly certified by Sectional ASTE/DSTE will be submitted alongwith the bill :
      1. Joint measurement and report as per prescribed format.
      2. Certification that the EI is working satisfactory in networking mode.
      3. Penalty calculation.
  • Other conditions -

    1. During the period of maintenance of contract, no third party will allowed to undertake any repairing/serving of the system unless the firm performing the CAMC consent but the firm will allow the Railway staff to perform any first line maintenance.
    2. All tools and other testing equipments for maintenance and failure rectification shall be arranged by the firm at its own cost. The firm should keep a stock of all the relevant cards, modules and components at respective station, so that after getting information of failure, the cards, modules and components are immediately available for replacement No. extra cost will be paid for this by Railway. No cards modules and components active or hot standby or spares will be taken away by the firm in any case without immediate replacement with similar working cards, modules and components. After replacement the report should be jointly signed by Railway representative & firm repetitive and submitted to Sr. DSTE/DDU office.
  • Mandatory updation of Labour data on Railway's sharmik kalian portal by contractor :-

    1. Contractor is to abide by the provisions of Payment of Wages act & Minimum Wages act in terms of clause 54 and 55 of Indian Railways General Condition of Contract. In order to ensure the same, an application has been developed and hosted on website 'www.shramikkalyan.indianrailways.gov.in'. Contractor shall register his firm/company etc. and upload requisite details of labour and their payment in this portal. These details shall be available in public domain. The Registration/ updation of Portal shall be done as under:
      1. Contractor shall apply for onetime registration of his company/firm etc. in the Shramikkalyan portal with requisite details subsequent to issue of Letter of Acceptance. Engineer shall approve the contractor's registration in the portal within 7 days of receipt of such request.
      2. Contractor once approved by any Engineer, can create password with login ID (PAN No.) for subsequent use of portal for all LoAs issued in his favour.
      3. The contractor once registered on the portal, shall provide details of his Letter of Acceptances (LoA) / Contract Agreements on shramikkalyan portal within 15 days of issue of any LoA for approval of concerned engineer. Engineer shall update (if required) and approve the details of LoA filled by contractor within 7 days of receipt of such request.
      4. After approval of LoA by Engineer, contractor shall fill the salient details of contract labours engaged in the contract and ensure updating of each wage payment to them on shramikkalyan portal on monthly basis.
      5. It shall be mandatory upon the contractor to ensure correct and prompt uploading of all salient details of engaged contractual labour & payments made thereof after each wage period.
    2. While processing payment of any 'On Account bill' or 'Final bill' or release of 'Advances' or 'Performance Guarantee / Security deposit', contractor shall submit a certificate to the Engineer or Engineer's representatives that "I have uploaded the correct details of contract labours engaged in connection with this contract and payments made to them during the wage period in Railway's Shramikkalyan portal at 'www.shramikkalyan.indianrailways.gov.in' till ____Month, ____Year."
  • POLICE VERIFICATION OF ANTECEDENTS OF CONTRACTUAL STAFF - Police verification of the antecedents of contractual staff engaged in works/service contracts is compulsory required in uploaded Performa.

  • GENERAL - The General Condition of Contract 2020 as amended up-to-date shall be binding in this contract in all matters not specifically covered by the conditions set forth in the Tender documents provided it is not otherwise repugnant to the context.

  • TOOLS & EQUIPMENTS Tools and Equipments required for maintenance of the work will have to be arranged by the Contractor without any extra cost to the Contractor.

  • DAMAGE TO RAILWAY PROPERTY The Railway Administration will not be responsible for loss or damage to the contractor's materials, equipment, tools & plants due to floods, theft or any other cause or causes whatsoever. The contractor shall be held responsible for any damage to Railway property like telephone lines, cables which may be caused by any of his action in connection with or in the execution of the work.

  • CREDENTIAL The contractor should have experience in similar kind of job earlier. Performance Certificate from other Government Organization for satisfactory completion of similar Job should be uploaded with the offer.

  • CONDITION OF PRICES The Tenderer is required to quote the unit rates against each item appearing in the schedule of work. The rates quoted by the Tenderer shall be inclusive of Excise Duty, Sale Tax, Local Taxes and all other incidental like handling, freight, insurance etc. as may be applicable. Necessary exemption certificate of Octroi/Entry fee will be furnished by the Contractor. The rate quoted by the Tenderer and accepted by the Railway shall hold good till the completion of work a no additional claim whatsoever will be admissible on account of fluctuation in market rates, increase in Taxes/levies/Tolls etc. or on imposition of new taxes/levies/tolls rates, increase in Taxes/levies/Tolls etc. or on imposition of new taxes/levies/tolls etc.

  • Income Taxes and Sales Tax Sales Tax (if applicable) or what so ever and Income Tax, Surcharge on Income Tax and any other taxes as applicable will be deducted from all bills of the Contractor (if applicable). Besides Workmen Service Tax or as applicable shall be deducted at source.

  • Communication; Tenderer will nominate his representative for communication between Railway and Tenderer. Tenderer will provided address and phone No. of representative so that any massage can be communicated.

  • General Conditions of Contract and Standard Specification of RDSO for E.I system ( M/s Siemens make)as amended up to date shall be binding in the contract in all matters.

  • Regular training camps for healthy maintenance to be arranged by the OEM/AMC provider at each Service Centre per quarter(once in three month) to Railway staffs of that section.

  • OEM/AMC provider should also check earth connectivity and power supply i.e. 220 V input. If any defect is there in earth connectivity and power supply, Railway will repair.

  • The balance sheet and all other financial documents attested/certified by the Chartered Accountant (CA) to substantiate fulfillment of Financial Eligibility Criteria should be with UDIN, failing which the offer shall be considered as incomplete and will be summarily rejected without any further reference".

Bidder declarations (18)

Undertakings

  • I/We have visited the works site and I/We am/are aware of the site conditions.

  • I/We also agree to keep this tender open for acceptance for a period of 60 days from the date fixed for opening of the same and in default. I/We will be liable for forfeiture of my/our Earnest Money.

  • I/We offer to do offer to do the work for east Central Railway at the Rates quoted in the attached schedule and hereby bine myself/ourselves to complete the work in all respect within period of completion prescribed in the NIT from the date of issue of letter of acceptance of the tender.

  • I/We also hereby agree to abide by the Indian Railways Standard General Condition of Contract 2022, with all correction slips up to date and to carry out the work according to the Special Conditions of Contract and Specifications of materials and works as laid down by Railway in the annexed Special Conditions/Specifications. Schedule of Rates with all correction slips up to date for the present contract.

  • And I/We have under stood and accept the stipulation that full value of the earnest money as prescribed in NIT, forwarded with this tender shall stand forfeited without prejudice to any other right or remedies in case my/our Tender is accepted and if I/We do not commence the work, within Fifteen days after receipt of orders to that effect.

  • Until a format agreement is prepared and executed, acceptance of this Tender shall constitute a binding contract between us and indicated in the letter of acceptance of my/our offer for this work.

  • Before submitting a tender, the tenderer will be deemed to have satisfied himself by actual inspection of the site and locality of the works, that all conditions liable to be encountered during the execution of the works are taken into account and that the rates he enters in the tender forms are adequate and all inclusive to accord with the provisions in Clause-37 of the Standard General Conditions of Contract for the completion of works to the entire satisfaction of the Engineer

  • I/We have read the various conditions to tender attached hereto and agree by the said conditions.

Certifications

  • I/we the tenderer (s) am/are signing this document after carefully reading the contents.

  • I/We the tenderer(s) also accept all the conditions of the tender and have signed all the pages in confirmation thereof.

  • I/we hereby declare that I/we have downloaded the tender documents from Indian Railway website www.ireps.gov.in . I/we have verified the content of the document from the website and there is no addition, no deletion or no alteration to the content of the tender document. In case of any discrepancy noticed at any stage i.e. evaluation of tenders, execution of work or final payment of the contract, the master copy available with the railway Administration shall be final and binding upon me/us.

  • I/we declare and certify that I/we have not made any misleading or false representation in the forms, statements and attachments in proof of the qualification requirements.

  • I/We also understand that my/our offer will be evaluated based on the documents/credentials submitted along with the offer and same shall be binding upon me/us.

  • I/We declare that the information and documents submitted along with the tender by me/us are correct and I/we are fully responsible for the correctness of the information and documents, submitted by us.

  • I/we certify that I/we the tenderer(s) is/are not blacklisted or debarred by Railways or any other Ministry / Department of Govt. of India from participation in tender on the date of submission of bids, either in individual capacity or as a HUF/ member of the partnership firm/LLP/JV/Society/Trust.

  • I/we understand that if the contents of the certificate submitted by us are found to be forged/false at any time during process for evaluation of tenders, it shall lead to forfeiture of the Bid Security and may also lead to any other action provided in the contract including banning of business for a period of upto two year. Further, I/we and all my/our constituents understand that my/our offer shall be summarily rejected.

  • I/we also understand that if the contents of the certificate submitted by us are found to be false/forged at any time after the award of the contract, it will lead to termination of the contract, along with forfeiture of Bid Security/Security Deposit and Performance guarantee and may also lead to any other action provided in the contract including banning of business for a period of upto two year.

  • I/We have read the clause regarding restriction on procurement from a bidder of a country which shares a land border with India and certify that I am/We are not from such a country or, if from such a country, have been registered with the competent Authority. I/We hereby certify that I/we fulfil all the requirements in this regard and am/are eligible to be considered (evidence of valid registration by the competent authority is enclosed)