10 facts from the tender

Technical Education Department Chhattisgarh published this goods tender on GeM on 12 Oct 2026, for Dhamtari, Chhattisgarh. The estimated value is ₹43.7 L and the EMD is ₹43,748. It closes on 2 Nov 2026, 12:00 pm IST. Bid number GEM/2026/B/8091854.

Timeline

  1. Published12 Oct 2026 · 11:17 am
  2. Reverse auctionIf the bid qualifies, after evaluation

Bidding

Bid type
Bid
Evaluation method
Total value wise evaluation
Packet type
Two Packet Bid
Reverse auction
Yes, H1-Highest Priced Bid Elimination
Total quantity
1,385

Buyer

Created by
15jpdansena
Location
Dhamtari · Chhattisgarh
Portal
GeM

Important dates

Published
12 Oct 2026, 11:17 am IST
Closes
2 Nov 2026, 12:00 pm IST

Items & delivery

123 items · 1 delivery location

Delivery location · all items

493773,Govt Polytechnic Dhamtari C G

Showing 123 of 123
01Constant Temperature Water BathQuantity1Delivery45 daysDetailsClose
Delivery
45 days
02IS Sieve Mechanical Sieve ShakerQuantity2Delivery45 daysDetailsClose
Delivery
45 days
03Coarse Aggregate SieveQuantity1Delivery45 daysDetailsClose
Delivery
45 days
04Coarse Aggregate Sieve SetQuantity1Delivery45 daysDetailsClose
Delivery
45 days
05PH MeterQuantity1Delivery45 daysDetailsClose
Delivery
45 days
06BOD BottlesQuantity30Delivery45 daysDetailsClose
Delivery
45 days
07BuretteQuantity30Delivery45 daysDetailsClose
Delivery
45 days
08PipetteQuantity30Delivery45 daysDetailsClose
Delivery
45 days
09Jar BottleQuantity30Delivery45 daysDetailsClose
Delivery
45 days
10Reagent Bottle 100 MlQuantity30Delivery45 daysDetailsClose
Delivery
45 days
11Wash Bottle 500 MlQuantity30Delivery45 daysDetailsClose
Delivery
45 days
12Piezoelectric TransducerQuantity5Delivery45 daysDetailsClose
Delivery
45 days
13LVDTQuantity2Delivery45 daysDetailsClose
Delivery
45 days
14Stroboscope TachometerQuantity1Delivery45 daysDetailsClose
Delivery
45 days
15Photoelectric TachometerQuantity1Delivery45 daysDetailsClose
Delivery
45 days
16ServomotorQuantity1Delivery45 daysDetailsClose
Delivery
45 days
17Stepper MotorQuantity2Delivery45 daysDetailsClose
Delivery
45 days
18Oil Hydraulic Trainer KitQuantity1Delivery45 daysDetailsClose
Delivery
45 days
19Pneumatic Trainer KitQuantity1Delivery45 daysDetailsClose
Delivery
45 days
20Lever Operated Directional Control ValveQuantity1Delivery45 daysDetailsClose
Delivery
45 days
21Rope Brake DynamometerQuantity1Delivery45 daysDetailsClose
Delivery
45 days
22Pony Brake Dynamometer ModelQuantity2Delivery45 daysDetailsClose
Delivery
45 days
23IDMT OVER CURRENT RELAY TESTING KITQuantity1Delivery45 daysDetailsClose
Delivery
45 days
24ELECTRO MECHANICAL TYPE EARTH FAULT RELAY TESTING KITQuantity1Delivery45 daysDetailsClose
Delivery
45 days
25TRANSMISSION LINE TRAINING SYSTEMQuantity1Delivery45 daysDetailsClose
Delivery
45 days
26SYMMETRICAL AND UNSYMMETRICAL FAULT DEMONSTRATOR TRAINERQuantity1Delivery45 daysDetailsClose
Delivery
45 days
27KELVINS DOUBLE BRIDGE TRAINER KITQuantity1Delivery45 daysDetailsClose
Delivery
45 days
28MAXWELS BRIDGE TRAINER KITQuantity1Delivery45 daysDetailsClose
Delivery
45 days
29LVDT TRAINER KITQuantity1Delivery45 daysDetailsClose
Delivery
45 days
30STRAIN GAUGE TRAINER KITQuantity1Delivery45 daysDetailsClose
Delivery
45 days
31RTD TRAINER KITQuantity1Delivery45 daysDetailsClose
Delivery
45 days
32MEASURMENT OF POWER AND POWER FACTOR IN RLC SERIES CIRCUITQuantity1Delivery45 daysDetailsClose
Delivery
45 days
33MEASUREMENT OF POWER AND POWER FACTOR IN RLC CIRCUIT PARALLELQuantity1Delivery45 daysDetailsClose
Delivery
45 days
34Trainer Star Delta ConnectionQuantity1Delivery45 daysDetailsClose
Delivery
45 days
35Molding BoxQuantity3Delivery45 daysDetailsClose
Delivery
45 days
36Molding BoxQuantity3Delivery45 daysDetailsClose
Delivery
45 days
37Hand RiddleQuantity5Delivery45 daysDetailsClose
Delivery
45 days
38ShovelQuantity5Delivery45 daysDetailsClose
Delivery
45 days
39RammersQuantity5Delivery45 daysDetailsClose
Delivery
45 days
40Sprue PinQuantity5Delivery45 daysDetailsClose
Delivery
45 days
41Mallet 4lbsQuantity10Delivery45 daysDetailsClose
Delivery
45 days
42Strike Off BarQuantity3Delivery45 daysDetailsClose
Delivery
45 days
43BellowQuantity5Delivery45 daysDetailsClose
Delivery
45 days
44Crucible 1LQuantity4Delivery45 daysDetailsClose
Delivery
45 days
45Crucible 2LQuantity4Delivery45 daysDetailsClose
Delivery
45 days
46Crucible 3LQuantity4Delivery45 daysDetailsClose
Delivery
45 days
47TongQuantity5Delivery45 daysDetailsClose
Delivery
45 days
48Drill And Screw Driver MachineQuantity1Delivery45 daysDetailsClose
Delivery
45 days
49Jig Saw MachineQuantity1Delivery45 daysDetailsClose
Delivery
45 days
50Oxy-acetylene Gas Welding SystemQuantity1Delivery45 daysDetailsClose
Delivery
45 days
51Rough Bastard FileQuantity20Delivery45 daysDetailsClose
Delivery
45 days
52Flat Smooth FileQuantity20Delivery45 daysDetailsClose
Delivery
45 days
53Round FileQuantity20Delivery45 daysDetailsClose
Delivery
45 days
54Round FileQuantity20Delivery45 daysDetailsClose
Delivery
45 days
55Triangular FileQuantity20Delivery45 daysDetailsClose
Delivery
45 days
56Triangular FileQuantity20Delivery45 daysDetailsClose
Delivery
45 days
57Half Round FileQuantity20Delivery45 daysDetailsClose
Delivery
45 days
58Half Round FileQuantity20Delivery45 daysDetailsClose
Delivery
45 days
59Square FileQuantity20Delivery45 daysDetailsClose
Delivery
45 days
60Square FileQuantity20Delivery45 daysDetailsClose
Delivery
45 days
61File CardQuantity20Delivery45 daysDetailsClose
Delivery
45 days
62File Handle WoodenQuantity500Delivery45 daysDetailsClose
Delivery
45 days
63Chisel ColdQuantity5Delivery45 daysDetailsClose
Delivery
45 days
64Screw Driver SetQuantity1Delivery45 daysDetailsClose
Delivery
45 days
65Spanner SetQuantity1Delivery45 daysDetailsClose
Delivery
45 days
66Tap And Die SetQuantity1Delivery45 daysDetailsClose
Delivery
45 days
67Vernier CaliperQuantity1Delivery45 daysDetailsClose
Delivery
45 days
68MicrometerQuantity1Delivery45 daysDetailsClose
Delivery
45 days
69MicrometerQuantity1Delivery45 daysDetailsClose
Delivery
45 days
70Screw GaugeQuantity1Delivery45 daysDetailsClose
Delivery
45 days
71Screw GaugeQuantity1Delivery45 daysDetailsClose
Delivery
45 days
72Steel RuleQuantity20Delivery45 daysDetailsClose
Delivery
45 days
73Ball Peen Hammer With HandleQuantity20Delivery45 daysDetailsClose
Delivery
45 days
74Ball Peen Hammer With HandleQuantity20Delivery45 daysDetailsClose
Delivery
45 days
75Sledge Hammer With HandleQuantity5Delivery45 daysDetailsClose
Delivery
45 days
76Sledge Hammer With HandleQuantity2Delivery45 daysDetailsClose
Delivery
45 days
77Calipers InsideQuantity20Delivery45 daysDetailsClose
Delivery
45 days
78Calipers OutsideQuantity20Delivery45 daysDetailsClose
Delivery
45 days
79Calipers Odd LegQuantity20Delivery45 daysDetailsClose
Delivery
45 days
80Vernier Height GaugeQuantity1Delivery45 daysDetailsClose
Delivery
45 days
81Center PunchQuantity10Delivery45 daysDetailsClose
Delivery
45 days
82Letter PunchQuantity1Delivery45 daysDetailsClose
Delivery
45 days
83Number PunchQuantity1Delivery45 daysDetailsClose
Delivery
45 days
84ScriberQuantity20Delivery45 daysDetailsClose
Delivery
45 days
85Try SquareQuantity20Delivery45 daysDetailsClose
Delivery
45 days
86Measuring TapeQuantity10Delivery45 daysDetailsClose
Delivery
45 days
87Grinding MachineQuantity1Delivery45 daysDetailsClose
Delivery
45 days
88Drill Bit SetQuantity1Delivery45 daysDetailsClose
Delivery
45 days
89Drill Bit SetQuantity1Delivery45 daysDetailsClose
Delivery
45 days
90Machine WiseQuantity2Delivery45 daysDetailsClose
Delivery
45 days
91Pipe WiseQuantity2Delivery45 daysDetailsClose
Delivery
45 days
92Hacksaw Frame Fixed TypeQuantity40Delivery45 daysDetailsClose
Delivery
45 days
93ReamerQuantity4Delivery45 daysDetailsClose
Delivery
45 days
94ReamerQuantity1Delivery45 daysDetailsClose
Delivery
45 days
95Counter BoreQuantity2Delivery45 daysDetailsClose
Delivery
45 days
96Counter ShankQuantity1Delivery45 daysDetailsClose
Delivery
45 days
97Cabinet PlainQuantity1Delivery45 daysDetailsClose
Delivery
45 days
98Socket Set And Screwdriver Bit Torx Ratchet Driver Tool KitQuantity1Delivery45 daysDetailsClose
Delivery
45 days
99Steel Industrial AlmirahQuantity1Delivery45 daysDetailsClose
Delivery
45 days
100DesktopQuantity26Delivery45 daysDetailsClose
Delivery
45 days
101LASER PRINTERQuantity2Delivery45 daysDetailsClose
Delivery
45 days
102UPSQuantity28Delivery45 daysDetailsClose
Delivery
45 days
103Vernier CallipersQuantity5Delivery45 daysDetailsClose
Delivery
45 days
104Vernier Callipers DigitalQuantity5Delivery45 daysDetailsClose
Delivery
45 days
105Micrometer Screw GaugeQuantity5Delivery45 daysDetailsClose
Delivery
45 days
106SpherometerQuantity5Delivery45 daysDetailsClose
Delivery
45 days
107Spring BalanceQuantity5Delivery45 daysDetailsClose
Delivery
45 days
108Electronic BalanceQuantity1Delivery45 daysDetailsClose
Delivery
45 days
109Simple Pendulum Stand TypeQuantity5Delivery45 daysDetailsClose
Delivery
45 days
110Bob PendulumQuantity3Delivery45 daysDetailsClose
Delivery
45 days
111Analog StopwatchQuantity5Delivery45 daysDetailsClose
Delivery
45 days
112Stop ClockQuantity5Delivery45 daysDetailsClose
Delivery
45 days
113Poiseulles Viscosity ApparatusQuantity2Delivery45 daysDetailsClose
Delivery
45 days
114Tuning Forks SetQuantity3Delivery45 daysDetailsClose
Delivery
45 days
115Double Rod Meter BridgeQuantity2Delivery45 daysDetailsClose
Delivery
45 days
116Plug KeyQuantity5Delivery45 daysDetailsClose
Delivery
45 days
117Optical Bench With ClampQuantity1Delivery45 daysDetailsClose
Delivery
45 days
118Drawing Board WoodenQuantity5Delivery45 daysDetailsClose
Delivery
45 days
119PentiometerQuantity2Delivery45 daysDetailsClose
Delivery
45 days
120Resistance Box Plug TypeQuantity1Delivery45 daysDetailsClose
Delivery
45 days
121Photoelectric ApparatusQuantity1Delivery45 daysDetailsClose
Delivery
45 days
122Diode LaserQuantity1Delivery45 daysDetailsClose
Delivery
45 days
123Digital Trainer KitQuantity1 piecesDelivery45 daysDetailsClose
Delivery
45 days

Specifications & requirements

Specification Name
बड के िलए आवTयक अनुमत मूZय /Bid Requirement (Allowed Values)
Facility to study and verify all logic gates
Yes
Facility to verify boolean identities and Demogran's Theorems
Yes
Number of Breadboard
2
Number of tie points per breadboard wth ± 25 tolerance
840
Number of data switches
12
Number of pulsar switches ( Push to On)
2
Range of fixed clock in Hz
1 Hz to 1 MHz in 7 steps
Type of connectivity
Screw terminals (PT 10)
Number of seven segment display with BCD Inputs
2
Number of dual color indicators to observe high/low logic, standard outputs
Others
Warranty in years
1
Size of breadboard in mm x mm
Others
Material of case provided for enclosing the kit
Stainless Steel
Number of connecting wires provided
100
Number of 2 mm to 1 mm patch cords provided
Others
Specification Name
बड के िलए आवTयक अनुमत मूZय /Bid Requirement (Allowed Values)
Number of 2 mm to 2 mm patch cords provided
Others
Availability of Built in Power Supply
Yes
Block Description Screen printed on glassy epoxy PCB
Yes
Availability of test report from govt/NABL/ILAC accredited lab covering all parameters
No
Copies of all certifications and reports to be provided to buyer on demand at time of supplies ,
NA ,Incase test reports not availabble

Tender documents

Bid files and supporting documents, linked directly from GeM.

Policy & contract references

Documents you must submit

  • Experience Criteria
  • Past Performance
  • Bidder Turnover
  • Certificate (Requested in ATC)
  • OEM Authorization Certificate
  • OEM Annual Turnover
Show all 7
  • Additional Doc 1 (Requested in ATC)

Eligibility

Experience

3 years

Min. turnover

₹21 L

a year, 3-year average

OEM turnover

₹86 L

Past performance

50%

of the bid quantity

Experience & turnover exemptions

Exemptions depend on the evidence and conditions specified in the bid.

Preferences & relaxations

  • MSE purchase preference
  • MII preference
  • Class-1/2 local suppliers
  • EMD exemption: no
  • Inspection required: no

Check each criterion against the tender notice before you bid.

Commercial conditions

EMD
₹43,748
Performance guarantee
Not required
Offer validity
180 days

Payment terms

Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

View PDF · p. 20

Buyer requirements & conditions

Buyer-added conditions from the bid document.

OPTION CLAUSE: The Purchaser reserves the right to increase or decrease the quantity to be ordered up to 25 percent of bid quantity at the time of placement of contract. The purchaser also reserves the right to increase the ordered quantity up to 25% of the contracted quantity during the currency of the contract at the contracted rates. The delivery period of quantity shall commence from the last date of original delivery order and in cases where option clause is exercised during the extended delivery period the additional time shall commence from the last date of extended delivery period. The additional delivery time shall be (Increased quantity ÷ Original quantity) × Original delivery period (in days), subject to minimum of 30 days. If the original delivery period is less than 30 days, the additional time equals the original delivery period. The Purchaser may extend this calculated delivery duration up to the original delivery period while exercising the option clause. Bidders must comply with these terms.

Manufacturer Authorization:Wherever Authorised Distributors/service providers are submitting the bid, Authorisation Form /Certificate with OEM/Original Service Provider details such as name, designation, address, e-mail Id and Phone No. required to be furnished along with the bid

03

Forms of EMD and PBG

View PDF · p. 86

Bidders can also submit the EMD with Account Payee Demand Draft in favour of PRINCIPAL BRP GOVT POLYTECHNIC DHAMTARI payable at DHAMTARI . Bidder has to upload scanned copy / proof of the DD along with bid and has to ensure delivery of hardcopy to the Buyer within 5 days of Bid End date / Bid Opening date.

04

Certificates

View PDF · p. 86

ISO 9001: The bidder or the OEM of the offered products must have ISO 9001 certification.

05

Certificates

View PDF · p. 86

Bidder's offer is liable to be rejected if they don't upload any of the certificates / documents sought in the Bid document, ATC and Corrigendum if any.

06

Service & Support

View PDF · p. 86

Dedicated /toll Free Telephone No. for Service Support : BIDDER/OEM must have Dedicated/toll Free Telephone No. for Service Support.

07

Service & Support

View PDF · p. 86

Escalation Matrix For Service Support : Bidder/OEM must provide Escalation Matrix of Telephone Numbers for Service Support.

08

Service & Support

View PDF · p. 86

Availability of Service Centres: Bidder/OEM must have a Functional Service Centre in the State of each Consignee's Location in case of carry-in warranty. (Not applicable in case of goods having on-site warranty). If service center is not already there at the time of bidding, successful bidder / OEM shall have to establish one within 30 days of award of contract. Payment shall be released only after submission of documentary evidence of having Functional Service Centre.

Warranty period of the supplied products shall be 3 years from the date of final acceptance of goods or after completion of installation, commissioning & testing of goods (if included in the scope of supply), at consignee location. OEM Warranty certificates must be submitted by Successful Bidder at the time of delivery of Goods. The seller should guarantee the rectification of goods in case of any break down during the guarantee period. Seller should have well established Installation, Commissioning, Training, Troubleshooting and Maintenance Service group in INDIA for attending the after sales service. Details of Service Centres near consignee destinations are to be uploaded along with the bid.

10

Buyer Added Bid Specific ATC

View PDF · p. 86

Buyer uploaded ATC document Click here to view the file.

Similar open tenders

Soonest first

Search similar in the explorerFind this tender in the explorer

Open on GeM