Title No 1 Procurement Of Mobile Power Supply Unit
- Delivery
- 60 days
Indian Army
Ministry of Defence › Department of Military Affairs
Delivers to
Dhemaji, Assam
Ministry of Defence published this goods tender on GeM on 9 Oct 2026, for Dhemaji, Assam. The EMD is ₹1.7 L. It closes on 19 Oct 2026, 10:00 am IST. Bid number GEM/2026/B/8137239.
5 items · Address masked by GeM
***********Dhemaji
GeM masks the full address in this document.No matching items. Try another name, code or schedule.
Bid files and supporting documents, linked directly from GeM.
Full bid details and conditions
Applies to items 1, 2, 3, 4, 5
Applies to items 1, 2, 3, 4, 5
Experience
3 years
Min. turnover
₹47 L
a year, 3-year average
OEM turnover
₹23 L
Past performance
80%
of the bid quantity
Yes | Partial | Turn over value - 23 (in lakhs)
View PDF · p. 2Yes | Partial | Turn over value - 11.5 (in lakhs)
View PDF · p. 2Exemptions depend on the evidence and conditions specified in the bid.
Check each criterion against the tender notice before you bid.
Buyer-added conditions from the bid document.
Actual delivery (and Installation & Commissioning (if covered in scope of supply)) is to be done at following address FOR BORARUPAK (250KM RADIUS FROM BORARUPAK) MILITARY STATION BORARUPAK DISTRICT UPPER SUBANSIRI ARUNACHAL PRADESH PIN CODE 791122 .
Bidder shall submit the following documents along with their bid for Vendor Code Creation:
Installation, Commissioning, Testing, Configuration, Training (if any - which ever is applicable as per scope of supply) is to be carried out by OEM / OEM Certified resource or OEM authorised Reseller.
OPTION CLAUSE: The Purchaser reserves the right to increase or decrease the quantity to be ordered up to 50 percent of bid quantity at the time of placement of contract. The purchaser also reserves the right to increase the ordered quantity up to 50% of the contracted quantity during the currency of the contract at the contracted rates. The delivery period of quantity shall commence from the last date of original delivery order and in cases where option clause is exercised during the extended delivery period the additional time shall commence from the last date of extended delivery period. The additional delivery time shall be (Increased quantity ÷ Original quantity) × Original delivery period (in days), subject to minimum of 30 days. If the original delivery period is less than 30 days, the additional time equals the original delivery period. The Purchaser may extend this calculated delivery duration up to the original delivery period while exercising the option clause. Bidders must comply with these terms.
Scope of supply includes Training: Number of employees to be trained 4 , Place for Training 250 KM RADIUS FROM BORARUPAK and Duration of training 6 days.
The successful bidder has to supply all essential accessories required for the successful installation and commissioning of the goods supplied. Besides standard accessories as per normal industry practice, following accessories must be part of supply and cost should be included in bid price: Nil .
Scope of supply (Bid price to include all cost components) : Supply Installation Testing Commissioning of Goods and Training of operators and providing Statutory Clearances required (if any)
IMPORTED PRODUCTS: In case of imported products, OEM or Authorized Seller of OEM should have a registered office in India to provide after sales service support in India. The certificate to this effect should be submitted.
Bidder's offer is liable to be rejected if they don't upload any of the certificates / documents sought in the Bid document, ATC and Corrigendum if any.
ISO 9001: The bidder or the OEM of the offered products must have ISO 9001 certification.
Material Test Certificate Should Be Sent Along with The Supply. The Material Will Be Checked by Buyer’s Lab & the Results of the Lab will be the Sole Criteria for Acceptance of the Item.
The bidder is required to upload, along with the bid, all relevant certificates such as BIS licence, type test certificate, approval certificates and other certificates as prescribed in the Product Specification given in the bid document.
Timely Servicing / rectification of defects during warranty period: After having been notified of the defects / service requirement during warranty period, Seller has to complete the required Service / Rectification within 15 days time limit. If the Seller fails to complete service / rectification with defined time limit, a penalty of 0.5% of Unit Price of the product shall be charged as penalty for each week of delay from the seller. Seller can deposit the penalty with the Buyer directly else the Buyer shall have a right to recover all such penalty amount from the Performance Security (PBG).Cumulative Penalty cannot exceed more than 10% of the total contract value after which the Buyer shall have the right to get the service / rectification done from alternate sources at the risk and cost of the Seller besides forfeiture of PBG. Seller shall be liable to re-imberse the cost of such service / rectification to the Buyer.
Buyer Added text based ATC clauses ADDITIONAL TERMS & CONDITION
Search similar in the explorerFind this tender in the explorer