Browse all bids
GeMOpenGoodsReverse auctionBOQ

Electric Change Lever 100Amp Switch, Bricks, Electric Cable 10mm 2 Core Copper Armoured Cabel, PVC Wall Panel 10 Inch X 10ft, Switch Board 10 Amp, Wiring Set R B And G, PVC Conduit Pipe, Wall Mounted…

Indian Army

Ministry of Defence › Department of Military Affairs

Delivers to

Jammu, Jammu and Kashmir

Overview

11 facts from the tender

Ministry of Defence published this goods tender on GeM on 10 Oct 2026, for Jammu, Jammu and Kashmir. No EMD is required. It closes on 12 Oct 2026, 3:00 pm IST. Bid number GEM/2026/R/749543.

From the bid document

TimelineBid → reverse auction

  1. Bid published12 Sep 2026
  2. Bid closed23 Sep 2026 · 10:00 am
  3. RA issued9 Oct 2026
  4. RA ends12 Oct 2026 · 3:00 pm

Bidding

Bid type
Reverse auction
Evaluation method
Total value wise evaluation
Packet type
Two Packet Bid
Reverse auction
Yes, 50% Lowest Priced Technically Qualified Bidders
Auction for bid
GEM/2026/B/8029749
Total quantity
20,199

Buyer

Created by
EPO@235
Location
Jammu · Jammu and Kashmir
Portal
GeM

Important dates

Published
10 Oct 2026, 3:00 pm IST
Closes
12 Oct 2026, 3:00 pm IST

Bid & reverse auction

This reverse auction is the price round of bid GEM/2026/B/8029749. GeM's auction document lists only the auction, so the items, delivery, eligibility and buyer terms below come from the bid document and are marked From the bid document.

Bid document (PDF) Reverse auction document (PDF)

Items & delivery

From the bid document

82 items · Address masked by GeM

Delivery location · all items

***********Jammu

GeM masks the full address in this document.
Showing 82 of 82
01Electric Change Lever 100Amp SwitchQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
02BricksQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
03Electric Cable 10mm 2 Core Copper Armoured CabelQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
04PVC Wall Panel 10 Inch X 10ftQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
05Switch Board 10 AmpQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
06Wiring Set R B And GQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
07PVC Conduit PipeQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
08Wall Mounted FanQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
09Exhaust Fan 200mmQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
1022W 8inch LED LightQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
11Ceiling Tiles Of Size 2ft X 2ftQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
12Wall Angle 10ftQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
13Maint T Channel 12ftQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
14Cross T Channel 4ftQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
15Cross T Channel 2ftQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
16GI Wire Hanger WireQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
17Black Screw 1 InchQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
18Grinding Disk 4inchQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
1963 Amp Change Over BoxQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
20Changeover Switch 100AmpQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
212 Inch GI Round Pipe 20ft LengthQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
22CGI Sheet 12ftQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
23Nut Bolts For Pipe And Tin SheetQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
24Armoured Cable 25 Sqmm 4 CoreQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
25Cement 43 OPC AkhnoorQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
26Cement 43 OPC HamirpurQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
27River Sand Conforming To IS- 2116-1980. At AkhnoorQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
28River Sand Conforming To IS- 2116-1980. At HamirpurQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
29Stone Agggraded 40 Mm Graded Confirming To IS 383 -1970 AkhnoorQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
30Stone Agggraded 40 Mm Graded Confirming To IS 383 -1970 HamirpurQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
31Crushed Stone Aggregate 20 Mm Graded Conforming To IS 383-1970. AkhnoorQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
32Crushed Stone Aggregate 20 Mm Graded Conforming To IS 383-1970. HamirpurQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
335 Amp SocketQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
34Crushed Stone Aggregate 40 Mm Graded Conforming To IS 383-1970. AkhnoorQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
35Tiles 2 Ft X 2FtQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
36False CeilingQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
37Door ClosureQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
38HingesQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
39Window GlassQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
40Tiles 2Ft X 4FtQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
41Taping Screw 3 InchQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
42Plywood 6x6x4mmQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
43Tiles 1Ft X 1FtQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
44PVC Pipe 4Inch X 20 FtQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
45Septic TankQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
46HandleQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
47Aluminium Door Jaali 6Ft X 8FtQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
48Tiles 1.5 Ft 1.5FtQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
49Aluminium Door FrameQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
50Toilet Sheet Indian With Complete FittingsQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
51PVC Cable Insulated And Un-sheathed 2.5 Sqmm Twin Core With Flxible Copper Conductor Suitable Upto 1100VQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
52PVC Cable Insulated And Un-sheathed 1.5 Single Core With Flxible Copper Upto 1100VQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
53Armoured Cable 16 Sqmm 4 CoreQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
54PVC Insulator Armd Hy Duty Electric 10 Sqmm Cable 2 CoreQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
55Cable 1 Sqmm Single Core CopperQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
56MCB 64 Amp DPQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
57Ceiling Light 2Ft X 2FtQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
58Bulb HolderQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
59Change Over 100 AmpQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
60Change Over 32 AmpQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
61Change Over 63 AmpQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
62Exhaust FanQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
63Fan RegulatorQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
64Fan CondenserQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
65LED Bulb 09WQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
66LED Bulb 10WQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
67LED Blub 15WQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
68LED Bulb 12WQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
69LED Bulb 18WQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
70CFL 20WQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
71LED Bulb 20WQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
72LED Light 45 WattQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
73Tube Light 18WQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
74Tube Light 20WQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
75Main Switch 63 Amp 3 PoleQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
76Main Switch 32 AmpQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
77Maint Switch 16 AmpQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
78MCB 10 AmpQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
79MCB 16 AMPQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
80MCB 32 AmpQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
81MCB 6 Amp SPQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days
82MCB 63 Amp With MCB BoxQuantityNot statedDelivery45 daysDetailsClose
Delivery
45 days

Tender documents

Bid files and supporting documents, linked directly from GeM.

Policy & contract references

Documents you must submit

  • Experience Criteria
  • Past Performance
  • Bidder Turnover
  • Certificate (Requested in ATC)
  • OEM Authorization Certificate
  • OEM Annual Turnover
Show all 8
  • Additional Doc 1 (Requested in ATC)
  • Compliance of BoQ specification and supporting document

Eligibility

From the bid and reverse-auction documents

Experience

3 years

Min. turnover

₹4 L

a year, 3-year average

OEM turnover

₹24 L

Past performance

80%

of the bid quantity

Experience & turnover exemptions

Micro & small enterprises (MSE)

Complete exemption
From the reverse auction
Exemption conditions

Yes | Complete

View PDF · p. 2

Exemptions depend on the evidence and conditions specified in the bid.

Preferences & relaxations

From the bid document

  • EMD exemption
  • Inspection required: no

Check each criterion against the tender notice before you bid.

Commercial conditions

From the bid document

EMD
Not required
Performance guarantee
5% for 24 months
Offer validity
180 days

Reverse auction extension

From the reverse auction

If any seller submits the offer price during last 30 minutes of RA end time, then RA will be automatically extended for next 30 minutes from the last participation time. There is no limit on such RA extension cycle.

View PDF · p. 2

Buyer requirements & conditions

Buyer-added conditions from the bid and the reverse-auction documents.

From the bid document

Actual delivery (and Installation & Commissioning (if covered in scope of supply)) is to be done at following address Akhnoor Jammu Jammu & Kashmir - - .

Bidder financial standing: The bidder should not be under liquidation, court receivership or similar proceedings, should not be bankrupt. Bidder to upload undertaking to this effect with bid.

Bidders are advised to check applicable GST on their own before quoting. Buyer will not take any responsibility in this regards. GST reimbursement will be as per actuals or as per applicable rates (whichever is lower), subject to the maximum of quoted GST %.

Bidder shall submit the following documents along with their bid for Vendor Code Creation:

  • a.Copy of PAN Card.
  • b.Copy of GSTIN.
  • c.Copy of Cancelled Cheque.
  • d.Copy of EFT Mandate duly certified by Bank.

Experience Criteria: The Bidder or its OEM {themselves or through reseller(s)} should have regularly, manufactured and supplied same or similar Category Products to any Central / State Govt Organization / PSU for 3 years before the bid opening date. Copies of relevant contracts to be submitted along with bid in support of having supplied some quantity during each of the year. In case of bunch bids, the primary product having highest value should meet this criterion.

Installation, Commissioning, Testing, Configuration, Training (if any - which ever is applicable as per scope of supply) is to be carried out by OEM / OEM Certified resource or OEM authorised Reseller.

Manufacturer Authorization:Wherever Authorised Distributors/service providers are submitting the bid, Authorisation Form /Certificate with OEM/Original Service Provider details such as name, designation, address, e-mail Id and Phone No. required to be furnished along with the bid

NON DISCLOSURE DECLARATION CERTIFICATE (On Bidder Letter Head) to be uploaded with bid:

  • 1.I M/s. M/s Bidder hereby declare that I shall not disclose the contract or any provision, specification, plan, design, pattern, sample or information thereof to any third party during and after expiry of Contract.
  • 2.If defying the norms as per the Contract a legal action may be taken against me as per the existing Rules.

OPTION CLAUSE: The Purchaser reserves the right to increase or decrease the quantity to be ordered up to 50 percent of bid quantity at the time of placement of contract. The purchaser also reserves the right to increase the ordered quantity up to 50% of the contracted quantity during the currency of the contract at the contracted rates. The delivery period of quantity shall commence from the last date of original delivery order and in cases where option clause is exercised during the extended delivery period the additional time shall commence from the last date of extended delivery period. The additional delivery time shall be (Increased quantity ÷ Original quantity) × Original delivery period (in days), subject to minimum of 30 days. If the original delivery period is less than 30 days, the additional time equals the original delivery period. The Purchaser may extend this calculated delivery duration up to the original delivery period while exercising the option clause. Bidders must comply with these terms.

Scope of supply includes Training: Number of employees to be trained 10 , Place for Training Akhnnor and Duration of training 7 days.

The Buyer has an existing set up / inventory of similar products. The offered / supplied product must be compatible with existing system. The bidder has to ensure Compatibility of the supplied items or shall have to include in the supply the necessary hardware / software to make them compatible at no extra cost to the buyer. The details of items with which compatibility is required are as under: All the defect rectification of teh supplied stores/items

The successful bidder has to supply all essential accessories required for the successful installation and commissioning of the goods supplied. Besides standard accessories as per normal industry practice, following accessories must be part of supply and cost should be included in bid price: All the taxes, transportation and labour charges etc .

Without prejudice to Buyer’s right to price adjustment by way of discount or any other right or remedy available to Buyer, Buyer may terminate the Contract or any part thereof by a written notice to the Seller, if:

  • i)The Seller fails to comply with any material term of the Contract. ii) The Seller informs Buyer of its inability to deliver the Material(s) or any part thereof within the stipulated Delivery Period or such inability otherwise becomes apparent. iii) The Seller fails to deliver the Material(s) or any part thereof within the stipulated Delivery Period and/or to replace/rectify any rejected or defective Material(s) promptly. iv) The Seller becomes bankrupt or goes into liquidation.
  • v)The Seller makes a general assignment for the benefit of creditors. vi) A receiver is appointed for any substantial property owned by the Seller. vii) The Seller has misrepresented to Buyer, acting on which misrepresentation Buyer has placed the Purchase Order on the Seller.

Nominated Inspection Agency: On behalf of the Buyer organization, any one of the following Inspection Agency would be conducting inspection of stores before acceptance: Pre-dispatch Inspection at Seller Premises (applicable only if pre-dispatch inspection clause has been selected in ATC): - Post Receipt Inspection at consignee site before acceptance of stores: Accepting Officer/Board of Officer/Any other nominated Officer

Testing of Sample: The testing of advance sample and bulk sample during PDI will be carried at the designated AHSP labs.When testing facilities are not available, the facilities of Govt labs/NABL/Accredited labs will be utilized. The testing charges outside the designated AHSP labs to be borne by seller's.

16

Forms of EMD and PBG

View PDF · p. 63

Bidders can also submit the EMD with Account Payee Demand Draft in favour of Commanding Officer 235 Engineer Regiment payable at SBI Akhnoor . Bidder has to upload scanned copy / proof of the DD along with bid and has to ensure delivery of hardcopy to the Buyer within 5 days of Bid End date / Bid Opening date.

17

Forms of EMD and PBG

View PDF · p. 63

Bidders can also submit the EMD with Banker’s Cheque in favour of Commanding Officer 235 Engineer Regiment payable at SBI Akhnoor . Bidder has to upload scanned copy / proof of the BC along with bid and has to ensure delivery of hardcopy to the Buyer within 5 days of Bid End date / Bid Opening date.

18

Forms of EMD and PBG

View PDF · p. 63

Successful Bidder can submit the Performance Security in the form of Account Payee Demand Draft also (besides PBG which is allowed as per GeM GTC). DD should be made in favour of Commanding Officer 235 Engineer Regiment payable at SBI Akhnoor . After award of contract, Successful Bidder can upload scanned copy of the DD in place of PBG and has to ensure delivery of hard copy to the original DD to the Buyer within 15 days of award of contract.

19

Forms of EMD and PBG

View PDF · p. 63

Successful Bidder can submit the Performance Security in the form of Fixed Deposit Receipt also (besides PBG which is allowed as per GeM GTC). FDR should be made out or pledged in the name of Commanding Officer 235 Engineer Regiment A/C (Name of the Seller). The bank should certify on it that the deposit can be withdrawn only on the demand or with the sanction of the pledgee. For release of Security Deposit, the FDR will be released in favour of bidder by the Buyer after making endorsement on the back of the FDR duly signed and stamped along with covering letter. Successful Bidder has to upload scanned copy of the FDR document in place of PBG and has to ensure delivery of hard copy of Original FDR to the Buyer within 15 days of award of contract.

20

Scope of Supply

View PDF · p. 64

Scope of supply (Bid price to include all cost components) : Only supply of Goods

21

Certificates

View PDF · p. 64

Bidder's offer is liable to be rejected if they don't upload any of the certificates / documents sought in the Bid document, ATC and Corrigendum if any.

22

Certificates

View PDF · p. 64

ISO 9001: The bidder or the OEM of the offered products must have ISO 9001 certification.

23

Certificates

View PDF · p. 64

Material Test Certificate Should Be Sent Along with The Supply. The Material Will Be Checked by Buyer’s Lab & the Results of the Lab will be the Sole Criteria for Acceptance of the Item.

24

Certificates

View PDF · p. 64

The bidder is required to upload, along with the bid, all relevant certificates such as BIS licence, type test certificate, approval certificates and other certificates as prescribed in the Product Specification given in the bid document.

25

Certificates

View PDF · p. 64

To be eligible for award of contract, Bidder / OEM must possess following Certificates / Test Reports on the date of bid opening (to be uploaded with bid): Test certificate/report of the bid items .

  • 26.Turnover Bidder Turn Over Criteria: The minimum average annual financial turnover of the bidder during the last three years, ending on 31st March of the previous financial year, should be as indicated in the bid document. Documentary evidence in the form of certified Audited Balance Sheets of relevant periods or a certificate from the Chartered Accountant / Cost Accountant indicating the turnover details for the relevant period shall be uploaded with the bid. In case the date of constitution / incorporation of the bidder is less than 3 year old, the average turnover in respect of the completed financial years after the date of constitution shall be taken into account for this criteria.
  • 27.Turnover OEM Turn Over Criteria: The minimum average annual financial turnover of the OEM of the offered product during the last three years, ending on 31st March of the previous financial year, should be as indicated in the bid document. Documentary evidence in the form of certified Audited Balance Sheets of relevant periods or a certificate from the Chartered Accountant / Cost Accountant indicating the turnover details for the relevant period shall be uploaded with the bid. In case the date of constitution / incorporation of the OEM is less than 3 year old, the average turnover in respect of the completed financial years after the date of constitution shall be taken into account for this criteria. In case of bunch bids, the OEM of CATEGORY RELATED TO primary product having highest bid value should meet this criterion.

Warranty period of the supplied products shall be 2 years from the date of final acceptance of goods or after completion of installation, commissioning & testing of goods (if included in the scope of supply), at consignee location. OEM Warranty certificates must be submitted by Successful Bidder at the time of delivery of Goods. The seller should guarantee the rectification of goods in case of any break down during the guarantee period. Seller should have well established Installation, Commissioning, Training, Troubleshooting and Maintenance Service group in INDIA for attending the after sales service. Details of Service Centres near consignee destinations are to be uploaded along with the bid.

Successful bidder will have to ensure that adequate number of dedicated technical service personals / engineers are designated / deployed for attending to the Service Request in a time bound manner and for ensuring Timely Servicing / rectification of defects during warranty period, as per Service level agreement indicated in the relevant clause of the bid.

Timely Servicing / rectification of defects during warranty period: After having been notified of the defects / service requirement during warranty period, Seller has to complete the required Service / Rectification within 7 days time limit. If the Seller fails to complete service / rectification with defined time limit, a penalty of 0.5% of Unit Price of the product shall be charged as penalty for each week of delay from the seller. Seller can deposit the penalty with the Buyer directly else the Buyer shall have a right to recover all such penalty amount from the Performance Security (PBG).Cumulative Penalty cannot exceed more than 10% of the total contract value after which the Buyer shall have the right to get the service / rectification done from alternate sources at the risk and cost of the Seller besides forfeiture of PBG. Seller shall be liable to re-imberse the cost of such service / rectification to the Buyer.

31

Buyer Added Bid Specific ATC

View PDF · p. 65

Buyer Added text based ATC clauses Bidder must follow the above mentioned additional Terms & Conditions. If Bidder fail to follow the same he can be disqualified by the Board of Officer/Accepting Officer. In case of any contradictory Terms & Conditio ns with respect to default Terms & Conditions mentioned on GeM & those uploaded in ATC, the Terms & C onditions of ATC will be adhered to and take preference. .

32

Buyer Added Bid Specific ATC

View PDF · p. 65

Buyer uploaded ATC document Click here to view the file.

From the reverse auction

Reverse auction — offer validity

View PDF · p. 2

Participation by the bidder in RA process would be considered as their consent for extension in offer validity by 30 days by the date of RA initiation.

Similar open tenders

Soonest first

Search similar in the explorerFind this tender in the explorer

Open on GeM