Ministry of Railways published this works tender on eProcure on 7 Oct 2026, for Mumbai. The estimated value is ₹1.7 Cr and the EMD is ₹3.4 L. It closes on 30 Oct 2026, 3:00 pm IST. Tender ID 92022773 · Ref RTM-2025-26-164R2.
Timeline
- Published7 Oct 2026
5:51 pm - Bidding starts16 Oct 2026
- Closes30 Oct 2026
3:00 pm
Key figures
Estimated value₹1.7 Cr
EMD₹3.4 L
Closing date30 Oct 20263:00 pm IST
Key facts
- Contract type
- Works - General · Expenditure
- Tender type
- Open
- Tendering section
- WA SECTION
- Bidding system
- Single Packet System
- Bidding style
- Single Rate for Each Schedule
- Validity of offer
- 60 days
- Completion period
- 10 Months
- Tender document cost
- None
- JV / consortium
- Not allowed
- Ranking order
- Lowest to Highest
- Expenditure type
- Capital (Works)
- Pre-bid meeting
- None
- Inviting officer
- Sr.DEN-Co/RTMRATLAM DIVISION-ENGINEERING/WESTERN RLY
Complies with the Public Procurement (Make in India) Order 2017
The tender inviting authority confirms this tender does not violate the GFR rules on procurement through GeM
Bidders from a country sharing a land border with India must be registered with the competent authority
About this tender
For complete description and other details, please refer to tender
- Reference
- RTM-2025-26-164R2
- Tender ID
- 92022773
- Bid type
- Open/Advertised
- Product category
- Railway related Products
- Organisation type
- Central Govt. Ministry/Department
- Location
- Mumbai
- Portal
- eProcure
- Inviting authority
- RATLAM DIVISION-ENGINEERING/WESTERN RLY
Schedule of work
| Item | Quantity | Railways’ estimated rate | Amount |
|---|---|---|---|
| 1DSR 2021 itemEscalation -25% | ₹1,58,74,049.09 | ||
| 11.) Ujjain - Electrical work in connection with upgradation & Replacement of Telecom Passenger Amenities and various facilities in connection of Simhastha 2028. (2.) Ratlam Division: - Upgradation and Replacement of Telecom Passenger Amenities at 08 stations (Simhastha 2028) | ₹12,03,135.68 | ||
| Total | ₹1,70,77,184.77 |
Bids quote a percentage above, below or at par with these rates · The total matches the advertised value.
Documents
- Notice inviting tenderOpen document
- manufacture letterRecommendedmakermanufacturerofcivilmaterials.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS 10 GCC 2022GCC2022CorrectionSlipNo10.pdfDirect link not supplied in the PDFView reference in PDF ↗
- PBG PERFORMAPBGPerformaforTenderdocument30Aug2025.pdfDirect link not supplied in the PDFView reference in PDF ↗
- PROCEDURE FOR PAYMENT OF CONTRACTORS BILL AS PER GSTProcedureforpaymentofContractorbillasperGSTImplementation_GST_290617.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS 7 GCC 2022GCC2022CorrectionSlipNo7.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS 8 GCC 2022GCC2022CorrectionSlipNo8.pdfDirect link not supplied in the PDFView reference in PDF ↗
- LETTER OF CREDITLETTEROFCREDITASMODEOFPAYMENT062018.pdfDirect link not supplied in the PDFView reference in PDF ↗
- safety rulesSafetyrules.pdfDirect link not supplied in the PDFView reference in PDF ↗
- SAFETY AT WORK SITEPROCEDUREORDERFORENSURINGSAFETYATWORKSITE.pdfDirect link not supplied in the PDFView reference in PDF ↗
- NORELATIVECERTIFICATENOrelativecertificate.pdfDirect link not supplied in the PDFView reference in PDF ↗
- engagement of retd. rly employeecertificateforrailwayemployeereengagement_1.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Termination preformaTERMINATIONCONTRACT.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS 5 of GCC 2022ACS5GCC2022.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS4dt 07Aug2307.08.23ACS4.pdfDirect link not supplied in the PDFView reference in PDF ↗
- contractor e- measurement book07.08.23LAUNCHEMB.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Bid Capacity Annexure VIBidCapacity-AnnexureVI.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Offloading Part-S-of WorkOffloadingPartSofworkRBLetterNo2022-CE-I-CT-GCC-2020- Polociydt27Apr2022.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Annexure VIA- Bid security FormatBidsecurityAnnexure-VIA.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Annexure VIB-Annual Cobntractual TurnoverFormatforAnnualcontractualturnoverAnnexure-VIB.pdfDirect link not supplied in the PDFView reference in PDF ↗
- GCC April 2022GCCAPRIL2022.pdfDirect link not supplied in the PDFView reference in PDF ↗
- MOU for JVMOUFORJVGCCAPRIL22WITHALLACS.pdfDirect link not supplied in the PDFView reference in PDF ↗
- AnnexureV as per ACS4dt 07Aug23AnnexureVasperACS4dt07.08.2023.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Annexure V -A for signature of constituent firm or constituent memberAnnexureVA.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS 6 of GCC 2022ACS6GCC2022.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS 2 dt 13Dec22ACS2dt13Dec22.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Advance Correction Slip 2 date 14.07.2022 for GCC April 2022ACS1GCCAPR2022.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS 3 date 26.04.2023ACS3dt26APR23.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Contractor s e- measurement book -e- MBLetterNo.2017-CE-I-CT-9date31May2023.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS 9 GCC 2022GCC2022CorrectionSlipNo9.pdfDirect link not supplied in the PDFView reference in PDF ↗
- LED Western Railway specificationWRProcurementofLEDlightfittingsSpecification.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Electrical Technical specificationTS750ElectricalTechnicalDocument.pdfDirect link not supplied in the PDFView reference in PDF ↗
- JPO for Composite WorkJPOforCompositeTenderofCivilandElectricalworksforBuildingWorks-R2.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Special Condition of Cementspecialconditionofcement2025.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS 12 of GCC Apr 2022GCC2022CorrectionSlipNo12_11zon.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Acceptance of E-Bank Guarantee in Works ContractsEBGLetterRailwayBoardGuideline16.06.2026.pdfDirect link not supplied in the PDFView reference in PDF ↗
- ACS 11 GCC 2022GCC2022CorrectionSlipNo11.pdfDirect link not supplied in the PDFView reference in PDF ↗
- Annexure-V(A)Annexure-V(A).pdfOpen document
Documents to submit
Commercial-Compliance
- Document optional
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Technical-Compliances
- Document required
The tenderer shall clearly specify whether the tender is submitted on his own (Proprietary Firm) or on behalf of a Partnership Firm / Company / Joint Venture (JV) / Registered Society / Registered Trust / HUF etc. The tenderer(s) shall enclose the attested copies of the constitution of their concern, and copy of PAN Card along with their tender. Tender Documents in such cases are to be signed by such persons as may be legally competent to sign them on behalf of the firm, company, association, trust or society, as the case may be.(para 14.1 page 17 GCC April 2022)
- Document required
As per instructions please attach proforma of ANNEXURE V-A this certificate is to be given by attorney/authorized signatory/each member of partnership firm / Joint Venture (JV)/ Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc.) Non submission of above certificate (s) by the bidder shall result in summarily rejection of his/their bid. It shall be mandatorily incumbent up on the tenderer to identify, state and submit the supporting documents duly self-attested / digitally signed by which they/he is qualifying the Qualifying Criteria mentioned in the Tender Document. Proforma is available in uploaded documents.
- Document required
Certificate of Information regarding Employment/Partnership etc. of Retired Railway Employees with the tender as per the attached Performa. As per clause No 16
- and
- of GCC Part-I April 2022 corrected up to date. (As per GCC -April 2022, Para 16, Page -19-20).
- Document required
Certificate of NO Relative being an employee of Western Railway as per attached Performa.
- Document optional
Joint Venture (JV) in works tenders. Refer GCC para no 17.1 to 17.15.3 of Part-I GCC -April 2022 corrected up to date. (As per GCC-April 2022, Para 17, Page -20 to 24). Joint Venture Firms Shall be applicable to the works tenders of value more than Rs. 10 Cores (Rupees ten crores)Advance Correction Slip No.1(Rly. Board letter No.2022/CE-I/CT/GCC-2022/Policy date 14.07.2022.)
Show all 10
- Document required
Participation of Partnership Firm in works tenders. Refer GCC para no 18.1 to 18.11 of Part-I April 2022 corrected up to date. (As per GCC -April 2022, Para 18, Page -25 to 27)
- Document required
The tenderer should upload the scan copy of EPFO and ESI registration number. However EPFO and ESI registration would be mandatory and documents towards EPFO and ESI registration must be submitted before execution of the agreement.
- Document optional
The tenderer shall be required to submit Bid Security in favour of Sr. DFM-Ratlam with the tender for due performance with the stipulation to keep the offer open till such date as specified in the tender, under condition of tender. (GCC April 2022 Part I Instructions to tenderers (ITT) para 5 Bid Security (1) (a,b,c),(2) (3)(i-viii). As per ACS 2 issued vide Rly. Board letter No.2022/CE-I/CT/GCC-2022/Policy date 13.12.2022:-(ii) The original Bank Guarantee should be delivered in person to the official nominated as indicated in the tender document within 5 working days before closing date for submission of bids. As pr ACS 5 RB No. 2022/CE- I/CT/GCC-2022/Policy date 20.10.2023:- Para 5(3) II The original bank guarantee should be delivered in person to the official nominated as indicated in the tender document before closing date for submission of bid.(i.e. excluding the last date of submission of bids).
- Document required
The tenderer should submit valid electrical contractor's license issued by any Government & should submit copy of the same along with the offer failing to which offer will not consider as technically suitable. (Electrical License on the Name of agency / person who will supervise and execute the Electrical work).
Eligibility
Standard Financial Criteria
- Document required
Advance Correction Slip No.1(Rly. Board letter No.2022/CE-I/CT/GCC-2022/Policy date 14.07.2022.) PLEASE ATTACH COPY OF AUDITED BALANCE SHEET.
- Document required
Advance Correction Slip No.1(Rly. Board letter No.2022/CE-I/CT/GCC-2022/Policy date 14.07.2022.) PLEASE ATTACH COPY OF ANNEXURE VI-B.(Proforma is available in document).
Financial Eligibility Criteria: The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited.
The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet.
However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover.
The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
Special Technical Criteria
- Document required
The tenderer should submit valid electrical contractor's license issued by any Government & should submit copy of the same along with the offer failing to which offer will not consider as technically suitable. (Electrical License on the Name of agency / person who will supervise and execute the Electrical work).
Defination of Similar Work Construction of any Building Work.
Standard Technical Criteria
- Document required
The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited:
- Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or
- Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or
- One similar work costing not less than the amount equal to 60% of advertised value of the tender.
In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited:
- Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or
- Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or
- One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender. Note for b(1): Separate completed works of minimum required values shall also be considered for fulfillment of technical eligibility criteria for different components.
In such cases, what constitutes a component in a composite work shall be clearly pre-defined with estimated tender cost of it, as part of the tender documents without any ambiguity.
For tenders having advertised value more than Rs. 20 crore wherein eligibility criteria includes bid capacity also, the tenderer will be qualified only if its available bid capacity is equal to or more than the total bid value of the present tender. Annexure VI of GCC April 2022 and Advance Correction Slip No.1(Rly. Board letter No.2022/CE-I/CT/GCC-2022/Policy date 14.07.2022.)
Work experience certificate from private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organisation, work experience certificate issued by Public listed company having average annual turnover of Rs 500 crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate has been issued by a person authorized by the Public listed company to issue such certificates. In case tenderer submits work experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details of payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate.
Defination of Similar Work Construction of any Building Work.
Partnership firm/Joint Venture (JV) / Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc.
Please submit a certificate in the prescribed format (please download the format from the link given below). Non submission of the certificate, or submission of certificate either not properly filled in, or in a format other than the prescribed format shall lead to summary rejection of your offer. ( Click here to download the Format of Self Certification)
Terms & conditions
General Instructions
Performance Guarantee As per ACS-11 dtd 13.03.2026 Para 16(4)(h) Introduced to GCC Apr2022 is as under Para 16(4)(h) If a tender is accepted on the quoted rates of bidder which is below the advertised tender value, an additional performance security shall be submitted by bider as below - Bid quoted Below 0 to 5 % (inclusive) of advertised cost - Additional Performance Guarantee (%) = NIL Bid quoted Below 5 % - of advertised cost - Additional Performance Guarantee (%) = 5%
CPWD DSR-2021 (Delhi Schedule of Rates) and CPWD Specifications- 2019 (or latest) shall be used for all works related to Building Works, Road Works and Horticulture works and other Miscellaneous works with effect from 16.01.2023 with latest Correction Slips issued from time to time by CPWD.
Signature on Receipts for Amount.
Every receipt for money which may become payable or for any security which may become transferable to the Contractors under these presents, shall, if signed in the partnership name by anyone of the partners of a Contractor's firm be a good and sufficient discharge to the Railway in respect of the moneys or security purported to be acknowledged thereby and in the event of death of any of the Contractor, partners during the pendency of the contract, it is hereby expressly agreed that every receipt by anyone of the surviving Contractor partners shall if so signed as aforesaid be good and sufficient discharge as aforesaid provided that nothing in this Clause contained shall be deemed to prejudice or effect any claim which the Railway may hereafter have against the legal representative of any Contractor partner so dying for or in respect to any breach of any of the conditions of the contract, provided also that nothing in this clause contained shall be deemed to prejudice or effect the respective rights or obligations of the Contractor partners and of the legal representatives of any deceased contractor partners interse. (GCC April 2022 para 53.)
Applicability of rules for this tender
GCC-April 2022 with upto date correction slip.
CPWD DSR-2018 (Delhi Schedule of Rates) and CPWD Specifications- 2019 (or latest) shall be used for all works related to Building Works, Road Works and Horticulture works and other Miscellaneous works with effect from 01.06.2021 with latest Correction Slips issued from time to time by CPWD.
Relevant IS-CODES AND RAILWAY CODES AND MANUALS.
In these Special Conditions of Contract the following terms shall have the meaning hereby assigned to them except where the context otherwise requires. (a)"General Condition of Contract" shall mean General Conditions of Contract-April 2022 as contained in Western Railway, Engineering Department "Indian Railways Unified standard specifications (works and materials)Vol-I &II".
"Specifications" shall mean the Specifications for Materials and Works of the Railway as specified under the authority of the Ministry of Railways or Chief Engineer or as amplified, added to or superseded by special specifications if any, appended to the Tender Forms. (GCC April 2022 Part I para I Instructions to tenderers (ITT).)
Show all 58
Standard Schedule of Rates (SSOR) shall mean the schedule of Rates adopted by the Railway, which includes-
- "Unified Standard Schedule of Rates of the Railway (USSOR)" i.e. the Standard Schedule of Rates of the Railway issued under the authority of the Chief Engineer from time to time, updated with correction slips issued up to date of inviting tender or as otherwise specified in the tender documents;
- "Delhi Schedule Of Rates (DSR)" i.e. the Standard Schedule of Rates published by Director General/ Central Public Works Department, Government of India, New Delhi, as adopted and modified by the Railway under the authority of the Chief Engineer from time to time, updated with correction slips issued up to date of inviting tender or as otherwise specified in the tender documents.
"If any dispute arises between the parties with respect to this agreement any application or suit shall be instituted only in the; court with the local limits or whose Jurisdiction, the Western Railway's Divisional Headquarters office is situated and both the parties shall be bound by this clause. (Head quarters letter no. CE-Circular No. 11/No. W/623/5/ARB/1 dt. 26.04.04)
Special Conditions
'Tenderers should submit their offer strictly in accordance with the terms and conditions of the tender document. Tenderer should not quote any deviation from the tender document and should not quote any conditions. Nevertheless, as an exception, if any unavoidable deviations or conditions are quoted by the tenderers, financial impact of each of such conditions / deviations on their quoted unit rates, in terms of Rupees per unit rate, shall be clearly mentioned by the tenderer in the tender offer. If any of the deviation / condition has no financial impact on the quoted rates, in such cases also, the tenderer must clearly mention its financial impact as 'NIL'. This is required for proper financial evaluation of such conditional / deviated offers. Conditional offers / offers with deviations, without quantified financial impact of each of the condition / deviation on the quoted rates, shall be considered as "incomplete" and shall be summarily rejected'. (In terms of CE(Works)CCG's Letter No. W.118/0/3/S.I(W6) dt. 27.06.16,). Any revision of rates / rebates submitted (quoted) through a separate letter whether enclosed with the bid (Tender Form) or submitted separately or mentioned elsewhere in the document other than specified place shall be summarily ignored and will not be considered. (para 3 of tender form second sheet)
SPECIAL PROVISION IN CONNECTION WITH PARA 26 (PAGE 56-57) OF GCC April 2022(As per Railway Bd's letter no 2012/CE-I/CT/0/20 dt 10/05/13)
(A) In terms of provisions of new Clause 26A.1 to the General Conditions of Contract (GCC), contractor shall also employ following Qualified Engineers during execution of the allotted work:
- One Qualified Graduate Engineer when cost of work to be executed is Rs. 200 lakh and above, and
- One Qualified Diploma Holder Engineer when cost of work to be executed is more than Rs. 25 lakh, but less than Rs. 200 lakh.
(B) Further, in case the contractor fails to employ the Qualified Engineer, as aforesaid in Para (A) above, he, in terms of provisions of Clause 26A.2 to the General Conditions of Contract, shall be liable to pay an amount of Rs. 40,000 and Rs. 25,000 for each month or part thereof for the default period for the provisions, as contained in Para A(a) and A(b) above respectively.
As per para 26 A.3 Part (II), No. of qualified Engineers required to be deployed by the Contractor for various activities contained in the works contract shall be specified in the tender documents as 'Special Condition of Contract' by the tender inviting authority." (As per GCC April 2022, Para 26-A, Page 56.
RESTRICTIONS ON ARBITRATION CLAUSES. (As per GCC April 2022, Para 64. (I), Page 97) Demand for Arbitration:- As per clause No 64, GCC part-II April 2022 corrected up-to date.
Settlement of disputes-Indian railway Arbitration and Conciliation Rules:- As per clause No 63, GCC part-II April 2022 corrected up-to date.
These special conditions shall prevail over existing clauses 63 and 64 of General Conditions of Contract.
The provision of clause 63 & 64 to the General Conditions of Contract will be applicable only for the settlement of claims or disputes between the parties for values less than or equal to 20% of the value of the contract provisions of clause 63 & 64 and (ii)When the claim of disputes are of value more than 20% the value of the contract, other relevant clause of the General Conditions of Contract will not be applicable and arbitration will not be a remedy for settlement of such dispute. The above special conditions shall prevail over existing clause 63 of the General Conditions of Contract.
GUIDELINE FOR THE MAINTENANCE PERIOD (As per GCC April 2022, Para 47, Page 82-83).
1)The tenderer/s shall be required to maintain the work effectively as mentioned in the special conditions in tender documents. Maintenance period will commence from the date of completion as per Clause No.47 of the General Conditions of Contract. Security deposit will not be released until maintenance period is completed. For Zonal contracts, please see para below.
2) However, for a zonal work, the maintenance period shall be as under As per Annexure-III, GCC part-I
- and
- April 2022 corrected up-to date.
- Repair and maintenance work including white/color washing: three calendar months from date of completion for each work-order.
- All new works except earth work: Six calendar months from date of completion for each work order.
3)To cover up monsoon period, the maintenance period will be extended in cases when required and contractor shall remain responsible for maintenance for this extended period also. The contractor shall make good and remedy at his own expense within such period as may be stipulated by the Engineer, any defect which may develop or may be before the expiry of this period and intimation of which has been sent to the contractor within seven days of the expiry of the said period by a letter, sent by hand delivery or by registered post. In case the contractor fails to make adequate arrangements to rectify the defects within seven days of the receipt of such notices, the Engineer without further notice may make his own arrangement to rectify the defects and the cost of such rectification shall be recovered from the Security Deposit of the contractor or from any other money due to the contractor under this or any other contract.
SPECIAL CONDITION FOR TAX DEDUCTION
(1) In respect of works, the contract value of which is more than Rs. 5,000/- each, a deduction of 2% on the taxable payment from each of the Contractor's bills shall be made in terms of section 194(C) of the Income Tax Act of 1961 & 1991. (From time to time TDS will also be deducted along with I. Tax as per extent rules.
(2)The Railway will deduct sales tax if leviable in a particular state where the work is going on, the gross amount of each bill while making payment to the contractor(s). The recovery shall be governed as per the guide lines & rates prescribed by the concerned State Government
(3) Any Other taxes The Contractor shall bear in full all taxes and royalties levied by the State Government and/or Central Government from time to time. This would be entirely a matter between the contractor and State Government/or Central Government. Railway will recover the taxes and royalties through final bills if the contractor fails to pay the taxes and royalties to the Government.
DETAILS OF INSPECTION REGISTER AND RECORDS ARE TO BE MAINTAINED BY TENDERER ARE AS FOLLOWS:
1)The Contractor/s shall maintain accurate records, plans and charts showing the dates and progress of all main operations and the Engineer shall have access to this information at all reasonable times. Records of tests made shall be handed over to the Engineer/s representative after carrying out the tests. The following registers will be maintained at site by the Contractor/s.
2)Site Order Register: The Contractor/s shall promptly acknowledge by putting his signature in the site order against any order given therein by the Engineer or his representative or his superior officers and comply with them. The Compliance shall be reported by the Contractor/s to the Engineer in good time so that it can be checked. 3)Labour Register: This register will be maintained to show daily strength of labour in different categories employed by the Contractor/s.
4)LOG book of events: All events are required to be chronologically logged in this book shift wise and date wise.
5)Cement & steel registers shall be maintained by the contractor.
APPLICABILITY OF PRICE VARIATION CLAUSE AS PER GCC CLAUSE 46A
Applicability Price Variation Clause (PVC) shall be applicable only in tender having advertised value above Rs.2 Crores. Provided further that, in a contract where PVC is applicable, following shall be outside the purview of price adjustment (i.e. shall be excluded from the gross value of the work for the purpose of price variation). GCC April 2022 page 69 and Advance Correction Slip No.1(Rly. Board letter No.2022/CE-I/CT/GCC- 2022/Policy date 14.07.2022.)
II. Price Variation Clause for Annual Maintenance Contract or Zonal Contract :- The price variation Clause of General Conditions of Contract shall not apply to a works contract which is either an Annual Maintenance Contract or a Zonal Contract as per Railway Boards letter No.2013/CE/I/CT/O/10-PVC-Pt.I dtd.27.01.2015.
As per PCE/CCG letter No.W118/0 Vol. II (W6) date 14.06.2019 The security deposit against the contract shall be released only after the contractor has submitted the final PVC bill.
Implementation of Contractor e Measurement Book (e MB) All contracts costing more than Rs.5 Crore Contractor s e-MB is mandatory and Contractor s e-MB shall be part of Tender Document. (Railway Board Letter No.2017/CE-I/CT/9 date 31.05.2023)
DISASTER MANAGMENT
"All the available vehicles and equipment's of the contractor can be drafted by the Railway Administration in case of accidents/natural calamities involving human lives. The payment for such drafting shall be made according to the rates as shall be fixed by the Engineer. However, if the contractor is not satisfied with the decision of the Engineer in this respect he may appeal to the Chief Engineer within 30 Days of getting the decision of the Engineer, supported by analysis of the rates claimed. The Chief Engineer's decision after hearing both the parties in the matter would be final and binding on the contractor and the Railway".
EMERGENCY WORK
In the event of any accident or failure occurring in the execution of work/ arising out of it which in the opinion of the Engineer requires immediate attention, the Railway may bring its own workmen or other agency/agencies to execute or partly execute the necessary work or carry out repairs if the Engineer-in-charge considers that the contractor(s) is/are not in a position to do so in time without giving any notice and charge the cost thereof, to be determined by the Engineer-in- charge, to the contractor.
DAMAGE BY ACCIDENT/ FLOOD/ TIDES OR NATURAL CALAMITIES
The Contractor shall take all precautions against damages from accidents, floods tides or other natural occurrences. He shall not be entitled to any compensation for his tools, plants, materials, machines and other equipment lost or damaged by any cause whatsoever. The Contractor shall be liable to make good the damage to any structure or part of a structure, plant or material of every description belonging to the Railway covered under the Contract, lost or damaged by him due to any cause during the course of execution of work. The Railway Administration will not be liable to pay the contractor any charge for rectification or repair to any damage which may have occurred from any cause what so ever.
Tender Credentials As per para no 11 of GCC April 2022 Part-I corrected up to date. Non-compliance with any of the conditions set forth therein above is liable to result in the tender being rejected clause no 12 Part-I of GCC April 2022 corrected up to date . (As per GCC April 2022, Para 11, Page 16-17)
Procedure for contractual payment after implementations of GST Act 2017 (Railway Board's letter no. 2017/CE-I/CT/4/GST dated 29/06/2017, CIRCULATED BY CE(WORKS) CCG vide letter no. W118/0 VOL. IX (W6) dated 30.06.2017 for implementation of GST ACT' 2017).
INCLUSION OF LETTER OF CREDIT AS MODE OF PAYMENT
Inclusion of LETTER OF CREDIT as mode of payment In works tenders or service tenders invited by railways through E tendering on IREPS, having advertising value of Rs.10 lakhs and above (as per railway Bd's letter no 2018/CE-I/CT/9 dt 04/06/2018.
SPECIFICATIONS AND SPECIAL CONDITIONS FOR SUPPLYING & UTILLIZING ORDINARY PORTLAND CEMENT
Cement condition Seperately Attached .
SPECIFICATION OF STEEL ITEMS REINFORCEMENT STEEL (TMT BARS) AND STRUCTURAL STEEL
(A)All Reinforcement Steel (TMT Bars) and structural Steel shall be procured as per specifications mentioned in BIS's documents - IS : 1786 and IS : 2062 respectively. Independent tests shall be conducted, wherever required, to ensure that the materials procured conform to the specifications. (B)Steel shall be procured only from those firms, which are established, reliable, indigenous and Primary producers of steel, having integrated steel plants (ISP), using iron ore as the basic raw material and having in-house iron rolling facilities, following by production of liquid steel and crude steel, as per Ministry of Steel's guidelines. e.g. "SAIL/TISCO/JINDAL/RINL/ESSAR/IISCO". (C)However, only certain isolated sections of structural steel, not being rolled by ISPs, can be procured from the authorized re-rollers of ISPs or authorized licensee of BIS having traceability system and who use billets produced by ISPs. (D)The steel procured shall be reasonably free from cracks, surface flaws, laminations, rough and imperfect edges and all other harmful defects. Steel sections, shall be free from excessive rust, scaling and pitting and shall be will protected. The decision of the Engineer regarding rejecting any steel section on account of any of the above defects shall be final and binding. (E)Structural steel work shall conform to the requirement as specified in Indian Railway Unified Standard Specifications (Works and Materials) Vol. I & II . (F)Necessary purchase bill along with test certificate for steel shall be obtained and submitted to the Engineer in Charge. Steel without the test certificate from approved laboratory/ Engineering College shall not be used in the work. Certified copy of the same shall be submitted to Divisional Office along with running bills/final bills. Steel shall be tested for Tensile strength and bend test as per IS : 1599 as specified in Indian Railway Unified Standard Specifications (Works and Materials) Vol. I & II. (G)Quantity for this item shall be calculated as per nominal weight of steel section for the actually used in the work. No payment will be made for the wastage and the contractor will be allowed to take away the scrap and excess steel away from site. (H)The contractor shall be responsible for getting the measurement of steel entered in to steel register and signed by the Engineer in charge of the work before concreting is done to avoid dispute regarding quantity of steel used in the work. (I)The rates quoted for this item is deemed to be inclusive of the cost of binding wire and no separate payment shall be admissible for the same. (J)The steel shall be kept by the contractor under his custody at the site of work and Railway will not be responsible for any theft thereof. (K) The quantity so payable under relevant item shall be restricted to the quantity as per approved plan/drawing and decision of the Engineer in Charge in this regard shall be final and binding upon the contractor.
Special Condition of Drawings
- Contractor will provide architectural drawings with elevations etc complete , structural design details/drawings, design calculations, GAD (i.e. foundation ,beams, lintel, column, roof etc. based on railway approved GAD and will get it approved from railway. Contractor will also submit 3 copies with soft copy (2 nos.CD/pen drive) to railway for the same.
- Design shall be followed for seismic zone no. 3 and should be resistant from various disasters occurs in seismic zone no.3 . Design shall be proof checked by IIT / NIT/ Govt engineering college which will be further got approved from railway before actual commencement of work.
- Contractor has to submit completion plan in 75 Micron double mate GARWARE or similar tracing film for each drawing indicating all minor, major detail based on actual execution and signed by site supervisor (SE/SSE Works) and concern ADEN before submission of final bill. In addition to Completion plan the contractor shall also submit the drawings stored on CD-ROM/pen drive) failing this a recovery at a rate of 20000/- (Rs. Twenty thousands only) shall be made.
- The rates quoted by contractor in this tender shall be inclusive of preparation and submission of architectural drawings , structural design etc and completion plan, nothing extra shall be paid on this account. (NOTE -Required in case where standard/approved design ,drawing is not available or as directed by engineer incharge.)
The said letter is attached for reference.
Technical-Compliances
Please see instructions below standard technical criteria for Latest ANNEXURE V. This is for verification / confirmation of the documents submitted for compliance of eligibility /qualifying criteria. As per RB's letter No 2022/CE-I/CT/CCG Correspondence dtd 14.05.2024 Clarification regarding submission of Annexure-V "On IREPS Module, a facility has already been created for online submission of Annexure-V. Therefore, the provision of downloading of Annexure-V of GCC & uploading of physical signed Annexure-V by the tenderer had been discontinued on IREPS"
Restrictions on the Employment of Retired Engineers of Railway Services Within One Year of their Retirement: As per GCC -April 2022, Para 59.9, Page -91.
Performance Bank Guarantee As per Clause No. 16.(4) of GCC Part-I, April 2022 corrected up to date. (As per GCC -April 2022, Para 16.(4), Page 48-49) Performa Attached.
Bidder declarations (11)
Undertakings
I/ We have visited the works site and I / We am / are aware of the site conditions.
I/we the tenderer (s) am/are signing this document after carefully reading the contents.
I/We the tenderer(s) also accept all the conditions of the tender and have signed all the pages in confirmation thereof.
I/we hereby declare that I/we have downloaded the tender documents from Indian Railway website www.ireps.gov.in . I/we have verified the content of the document from the website and there is no addition, no deletion or no alteration to the content of the tender document. In case of any discrepancy noticed at any stage i.e. evaluation of tenders, execution of work or final payment of the contract, the master copy available with the railway Administration shall be final and binding upon me/us.
I/we declare and certify that I/we have not made any misleading or false representation in the forms, statements and attachments in proof of the qualification requirements.
I/We also understand that my/our offer will be evaluated based on the documents/credentials submitted along with the offer and same shall be binding upon me/us.
I/We declare that the information and documents submitted along with the tender by me/us are correct and I/we are fully responsible for the correctness of the information and documents, submitted by us.
I/we certify that I/we the tenderer(s) is/are not blacklisted or debarred by Railways or any other Ministry / Department of Govt. of India from participation in tender on the date of submission of bids, either in individual capacity or as a HUF/ member of the partnership firm/LLP/JV/Society/Trust.
I/we understand that if the contents of the certificate submitted by us are found to be forged/false at any time during process for evaluation of tenders, it shall lead to forfeiture of the Bid Security and may also lead to any other action provided in the contract including banning of business for a period of upto two year. Further, I/we and all my/our constituents understand that my/our offer shall be summarily rejected.
I/we also understand that if the contents of the certificate submitted by us are found to be false/forged at any time after the award of the contract, it will lead to termination of the contract, along with forfeiture of Bid Security/Security Deposit and Performance guarantee and may also lead to any other action provided in the contract including banning of business for a period of upto two year.
I/We have read the clause regarding restriction on procurement from a bidder of a country which shares a land border with India and certify that I am/We are not from such a country or, if from such a country, have been registered with the competent Authority. I/We hereby certify that I/we fulfil all the requirements in this regard and am/are eligible to be considered (evidence of valid registration by the competent authority is enclosed)
Fees & money
- EMD
- ₹3.4 L
- Tender fee
- None
Important dates
- Published
- 7 Oct 2026, 5:51 pm IST
- Bidding starts
- 16 Oct 2026
- Closes
- 30 Oct 2026, 3:00 pm IST
Similar open tenders
- TELECOM WORKS In CONNECTION WITH (1) Vadodara: Improvement of Passenger Amenities. (2) Va…Ministry of Railways · Closes 15 Oct 2026
- Telecom work for Augmentation of passenger s amenities by the extension of PF shed, water…Ministry of Railways · Closes 9 Oct 2026
- Composite Work (Civil, Electrical & S&T) comprising formation, viaducts, minor/major brid…Ministry of Railways · Closes 22 Oct 2026
- Composite Work (Civil, Electrical & S&T) comprising formation, viaducts, minor/major brid…Ministry of Railways · Closes 22 Oct 2026
- 1. KZJ-BPQ section: Telecom Proposal for Upgradation of Passenger amenities at Odela Rail…Ministry of Railways · Closes 28 Oct 2026
- Supply, installation, testing and commissioning of Telecom material in connection with (i…Ministry of Railways · Closes 9 Oct 2026
- Vadodara Division: Provision of Passenger Escalators at 12.0-meter-wide FOB (including ci…Ministry of Railways · Closes 21 Oct 2026
- Execution of Signaling & Telecommunication work in connection with: (1) Construction of n…Ministry of Railways · Closes 16 Oct 2026
Search similar in the explorerFind this tender in the explorer