Browse all bids
GeMOpenGoodsBidBOQ

FLANGES AND FITTINGS FOR CAPACITY AUGMENTATION OF DUPL DPPL

Gail India Limited

Ministry of Petroleum and Natural Gas › GAIL India Limited › Noida

Delivers to

Gautam Buddha Nagar, Uttar Pradesh

Overview

10 facts from the tender

Ministry of Petroleum and Natural Gas published this goods tender on GeM on 13 Oct 2026, for Gautam Buddha Nagar, Uttar Pradesh. The EMD is ₹2.8 L. It closes on 3 Nov 2026, 3:00 pm IST. Bid number GEM/2026/B/8151979.

Timeline

  1. Published13 Oct 2026 · 4:12 pm

Bidding

Bid type
Bid
Evaluation method
Group wise evaluation
Packet type
Two Packet Bid
Reverse auction
No
Total quantity
770

Buyer

Created by
buycon165.gil.up
Location
Gautam Buddha Nagar · Uttar Pradesh
Portal
GeM

Important dates

Published
13 Oct 2026, 4:12 pm IST
Closes
3 Nov 2026, 3:00 pm IST

Items & delivery

62 items · 1 delivery location

Delivery location · all items

201301,B - 35 & 36, Jubilee Tower, Gail (India) Limited, Sector - 1, Noida

Showing 62 of 62
01Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flanges MR No.A1Quantity5Delivery112 daysDetailsClose
Delivery
112 days
02Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flanges MR No.A1Quantity5Delivery112 daysDetailsClose
Delivery
112 days
03Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flanges MR No. A2Quantity18Delivery112 daysDetailsClose
Delivery
112 days
04Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flanges MR No. A2Quantity18Delivery112 daysDetailsClose
Delivery
112 days
05Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flangess MR No. A3Quantity14Delivery112 daysDetailsClose
Delivery
112 days
06Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flanges MR No. A3Quantity14Delivery112 daysDetailsClose
Delivery
112 days
07Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flanges MR No.A 4Quantity18Delivery112 daysDetailsClose
Delivery
112 days
08Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flanges MR No. A4Quantity18Delivery112 daysDetailsClose
Delivery
112 days
09Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flanges MR No. A5Quantity18Delivery112 daysDetailsClose
Delivery
112 days
10Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flanges MR No. A5Quantity18Delivery112 daysDetailsClose
Delivery
112 days
11(Hमशः 2ेणी 1 और 2ेणी 2 के 0थानीय आपूित%कता% के lप म4 अह%ता ?ाm करने के िलए आवPयक/Minimum 50% and 20% LocalQuantity66Delivery112 daysDetailsClose
Delivery
112 days
12Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Flangess MR No. A6Quantity66Delivery112 daysDetailsClose
Delivery
112 days
13Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Blind Flangess MR No. B1Quantity2Delivery112 daysDetailsClose
Delivery
112 days
14Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Blind Flangess MR No. B1Quantity2Delivery112 daysDetailsClose
Delivery
112 days
15Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Blind Flangess MR No. B2Quantity10Delivery112 daysDetailsClose
Delivery
112 days
16Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Blind Flangess MR No. B2Quantity10Delivery112 daysDetailsClose
Delivery
112 days
17Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Blind Flangess MR No. B3Quantity2Delivery112 daysDetailsClose
Delivery
112 days
18Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Blind Flangess MR No. B3Quantity2Delivery112 daysDetailsClose
Delivery
112 days
19Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Spectacle Blind Spacer And Blind MR No. C1Quantity3Delivery112 daysDetailsClose
Delivery
112 days
20Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Spectacle Blind Spacer And Blind MR No. C1Quantity3Delivery112 daysDetailsClose
Delivery
112 days
21Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Spectacle Blind Spacer And Blind MR No. C2Quantity3Delivery112 daysDetailsClose
Delivery
112 days
22Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Spectacle Blind Spacer And Blind MR No. C2Quantity3Delivery112 daysDetailsClose
Delivery
112 days
23Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Spectacle Blind Spacer And Blind MR No. C3Quantity5Delivery112 daysDetailsClose
Delivery
112 days
24(Hमशः 2ेणी 1 और 2ेणी 2 के 0थानीय आपूित%कता% के lप म4 अह%ता ?ाm करने के िलए आवPयक/Minimum 50% and 20% LocalQuantity5Delivery112 daysDetailsClose
Delivery
112 days
25Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Spectacle Blind Spacer And Blind MR No. C4Quantity10Delivery112 daysDetailsClose
Delivery
112 days
26Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Spectacle Blind Spacer And Blind MR No. C4Quantity10Delivery112 daysDetailsClose
Delivery
112 days
27Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Spectacle Blind Spacer And Blind MR No. C5Quantity16Delivery112 daysDetailsClose
Delivery
112 days
28Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Spectacle Blind Spacer And Blind MR No. C5Quantity16Delivery112 daysDetailsClose
Delivery
112 days
29Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Weldolets MR No. D1Quantity8Delivery112 daysDetailsClose
Delivery
112 days
30Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Weldolets MR No. D1Quantity8Delivery112 daysDetailsClose
Delivery
112 days
31Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Weldolets MR No. D2Quantity14Delivery112 daysDetailsClose
Delivery
112 days
32Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Weldolets MR No. D2Quantity14Delivery112 daysDetailsClose
Delivery
112 days
33Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Concentric Reducer MR No. E1Quantity14Delivery112 daysDetailsClose
Delivery
112 days
34Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Concentric Reducer MR No. E1Quantity14Delivery112 daysDetailsClose
Delivery
112 days
35Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Concentric Reducer MR No. E2Quantity7Delivery112 daysDetailsClose
Delivery
112 days
36Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Concentric Reducer MR No. E2Quantity7Delivery112 daysDetailsClose
Delivery
112 days
37(Hमशः 2ेणी 1 और 2ेणी 2 के 0थानीय आपूित%कता% के lप म4 अह%ता ?ाm करने के िलए आवPयक/Minimum 50% and 20% LocalQuantity14Delivery112 daysDetailsClose
Delivery
112 days
38Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F1Quantity14Delivery112 daysDetailsClose
Delivery
112 days
39Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F2Quantity7Delivery112 daysDetailsClose
Delivery
112 days
40Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F2Quantity7Delivery112 daysDetailsClose
Delivery
112 days
41Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F3Quantity7Delivery112 daysDetailsClose
Delivery
112 days
42Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F3Quantity7Delivery112 daysDetailsClose
Delivery
112 days
43Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F4Quantity45Delivery112 daysDetailsClose
Delivery
112 days
44Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F4Quantity45Delivery112 daysDetailsClose
Delivery
112 days
45Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F5Quantity18Delivery112 daysDetailsClose
Delivery
112 days
46Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F5Quantity18Delivery112 daysDetailsClose
Delivery
112 days
47Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F6Quantity26Delivery112 daysDetailsClose
Delivery
112 days
48Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 90 Degree Elbow MR No. F6Quantity26Delivery112 daysDetailsClose
Delivery
112 days
49Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel 45 Degree Elbow MR No. G1Quantity5Delivery112 daysDetailsClose
Delivery
112 days
50(Hमशः 2ेणी 1 और 2ेणी 2 के 0थानीय आपूित%कता% के lप म4 अह%ता ?ाm करने के िलए आवPयक/Minimum 50% and 20% LocalQuantity5Delivery112 daysDetailsClose
Delivery
112 days
51Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H1Quantity3Delivery112 daysDetailsClose
Delivery
112 days
52Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H1Quantity3Delivery112 daysDetailsClose
Delivery
112 days
53Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H2Quantity3Delivery112 daysDetailsClose
Delivery
112 days
54Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H2Quantity3Delivery112 daysDetailsClose
Delivery
112 days
55Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H3Quantity5Delivery112 daysDetailsClose
Delivery
112 days
56Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H3Quantity5Delivery112 daysDetailsClose
Delivery
112 days
57Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H4Quantity11Delivery112 daysDetailsClose
Delivery
112 days
58Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H4Quantity11Delivery112 daysDetailsClose
Delivery
112 days
59Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H5Quantity3Delivery112 daysDetailsClose
Delivery
112 days
60Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H5Quantity3Delivery112 daysDetailsClose
Delivery
112 days
61Ex Works Price Incl Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H6Quantity5Delivery112 daysDetailsClose
Delivery
112 days
62Inland Transportation And Other Charges As Per Clause K Iii Of Section II Of Tender Incl. GST For Carbon Steel Tees MR No. H6Quantity5Delivery112 daysDetailsClose
Delivery
112 days

Tender documents

Bid files and supporting documents, linked directly from GeM.

Policy & contract references

Documents you must submit

  • Experience Criteria
  • Certificate (Requested in ATC)
  • OEM Authorization Certificate
  • OEM Annual Turnover
  • Additional Doc 1 (Requested in ATC)
  • Additional Doc 2 (Requested in ATC)
Show all 8
  • Additional Doc 3 (Requested in ATC)
  • Additional Doc 4 (Requested in ATC)

Eligibility

Experience & turnover exemptions

Exemptions depend on the evidence and conditions specified in the bid.

Preferences & relaxations

  • MSE purchase preference
  • MII preference
  • Class-1/2 local suppliers
  • EMD exemption: no
  • Inspection required: no

Check each criterion against the tender notice before you bid.

Commercial conditions

EMD
₹281,650
Performance guarantee
5% for 31 months
Offer validity
90 days

Payment terms

Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

View PDF · p. 4

Buyer requirements & conditions

Buyer-added conditions from the bid document.

OPTION CLAUSE: The Purchaser reserves the right to increase or decrease the quantity to be ordered up to 25 percent of bid quantity at the time of placement of contract. The purchaser also reserves the right to increase the ordered quantity up to 25% of the contracted quantity during the currency of the contract at the contracted rates. The delivery period of quantity shall commence from the last date of original delivery order and in cases where option clause is exercised during the extended delivery period the additional time shall commence from the last date of extended delivery period. The additional delivery time shall be (Increased quantity ÷ Original quantity) × Original delivery period (in days), subject to minimum of 30 days. If the original delivery period is less than 30 days, the additional time equals the original delivery period. The Purchaser may extend this calculated delivery duration up to the original delivery period while exercising the option clause. Bidders must comply with these terms.

02

Buyer Added Bid Specific ATC

View PDF · p. 46

Buyer Added text based ATC clauses EMD AMOUNT AS SPECIFIED IN CLAUSE 2.0 (F) OF SECTION I (IFB) OF VOL-I OF TENDER SHALL PREVAIL. IN CASE OF AMBIGUITY OF EMD AMOUNT WITH GEM BIDDING DOCUMENT, THE UPLOADED TENDER DOCUME NT SHALL PREVAIL. UNITS OF QUANTITIES SELECTED IN THE GEM CATALOGUE STAND SUPERSEDED BY THE UNITS OF QUANTIT IES MENTIONED IN THE MR OF VOLUME-II OF THE TENDER DOCUMENT. ACCORDINGLY, THE MR OF THE TE NDER SHALL PREVAIL AND BE FOLLOWED. ALL TERMS AND CONDITIONS ARE STRICTLY AS PER UPLOADED TENDER DOCUMENT. .

03

Buyer Added Bid Specific ATC

View PDF · p. 46

Buyer uploaded ATC document Click here to view the file.

Similar open tenders

Soonest first

Search similar in the explorerFind this tender in the explorer

Open on GeM