11 facts from the tender

Ministry of Defence published this goods tender on GeM on 14 Oct 2026, for Barmer, Rajasthan. The EMD is ₹90,000. It closes on 15 Oct 2026, 2:00 pm IST. Bid number GEM/2026/R/751841.

From the bid document

TimelineBid → reverse auction

  1. Bid closed10 Oct 2026 · 5:00 pm
  2. RA issued13 Oct 2026
  3. RA ends15 Oct 2026 · 2:00 pm

Bidding

Bid type
Reverse auction
Evaluation method
Total value wise evaluation
Packet type
Two Packet Bid
Reverse auction
Yes, H1-Highest Priced Bid Elimination
Auction for bid
GEM/2026/B/8093186
Total quantity
509

Buyer

Created by
sbso@cweafjais
Location
Barmer · Rajasthan
Portal
GeM

Important dates

Published
14 Oct 2026, 2:00 pm IST
Closes
15 Oct 2026, 2:00 pm IST

Bid & reverse auction

This reverse auction is the price round of bid GEM/2026/B/8093186. GeM's auction document lists only the auction, so the items, delivery, eligibility and buyer terms below come from the bid document and are marked From the bid document.

Bid document (PDF) Reverse auction document (PDF)

Items & delivery

From the bid document

20 items · Address masked by GeM

Delivery location · all items

***********Barmer

GeM masks the full address in this document.
Showing 20 of 20
01Design Supply Installation Testing And Commissioning Of Air Cooled Floor Mounted Package Units Of Cap 7 Point 5 TR With Hermetically Sealed Scroll Type Compressor DX Coil Aircooled As Per ATCQuantity2Delivery90 daysDetailsClose
Delivery
90 days
02Supply And Fixing Of Copper Refrigerant Piping For Discharge Line From Indoor Unit To Outdoor Air Cooled Fan With 5 Or 8 Inches Pipe With Fitting Complete All As Per Site RequirementQuantity10Delivery90 daysDetailsClose
Delivery
90 days
03Supply And Fixing Of Copper Refrigerant Piping For Liquid Line From Indoor Unit To Outdoor Air Cooled Fan With 7 Or 8 Inches Pipe With Fitting CompleteQuantity10Delivery90 daysDetailsClose
Delivery
90 days
04Supply And Fixing Of 22 Gauge GI Sheet Ducting With All Fittings Such As Tee Bends Tunings Vanes Flange Etc Made Of GI Sheet Of Class VIII As Per IS 277 Fabricated As Per IS 655 Incl As Per ATCQuantity85Delivery90 daysDetailsClose
Delivery
90 days
05Supply And Fixing Black Flexible Closed Cell 19mm Thick Elastomeric Thermal Insulation Made Of Elastomeric Foam Based On Synthetic Rubber NBR Or PVC Tested For Maximum Service As Per ATCQuantity90Delivery90 daysDetailsClose
Delivery
90 days
06Supply And Fixing Of Supply Air Grill Or Diffusers Made Of Aluminium Section Powder Coated With Volume Control Damper Complete All As Per Site RequirementQuantity2Delivery90 daysDetailsClose
Delivery
90 days
07Supply And Fixing Of Return Air Grill Or Diffusers Made Of Aluminium Section Powder Coated Without Volume Control Damper Complete All As Per Site RequirementQuantity2Delivery90 daysDetailsClose
Delivery
90 days
08Supply And Fixing Of Fresh Air Grill With Damper Made Of GI Sheet 18 G Complete With Bird Screen Complete All As Per Site RequirementQuantity5Delivery90 daysDetailsClose
Delivery
90 days
09Supply And Fixing Of Flexible Canvas Connection Made Of Fire Retardant Cloth For PAC Units Complete All As Per Site RequirementQuantity5Delivery90 daysDetailsClose
Delivery
90 days
10Design Fabricate Supply Testing And Commissioning Of CPRI Approved Factory Made LT Panel Board Cubicle Type Suitable For Incoming Outgoings MCCB Or MCBs Double Door Outdoor As Per ATCQuantity1Delivery90 daysDetailsClose
Delivery
90 days
11M And L For Eart Hing Complete With GI Plate Electrode Of Size 600x600x6mm Thick Bured Directly In Ground Vertically At A Depth Not Less 2 Point 25M Below Normal Ground Level As Per ATCQuantity2Delivery90 daysDetailsClose
Delivery
90 days
12Complete As Per ATCQuantity65Delivery90 daysDetailsClose
Delivery
90 days
13Supply And Laying Double Wall Corrugated HDPE Duct Pipe 80mm Outer Dia Conforming To IS 14930 Part II Of Approved Coour With Fitting For Cable Protection Complete Laid Inas Per ATCQuantity60Delivery90 daysDetailsClose
Delivery
90 days
14Supply And Laying In Ground In Ducts In Pipes On Cable Trays Of PVC Insulated Aluminum Conductor Armoured Cables Of 1 Point 1KV Grade Confirming To IS Complete As Per ATCQuantity25Delivery90 daysDetailsClose
Delivery
90 days
15Supply And Fixing Or Laying GE Earth Strip 25mm X 4mm Below Ground In 40mm GI Pipe Wherever Required And On Surface Or In Recess For Connections EtcQuantity30Delivery90 daysDetailsClose
Delivery
90 days
16Supply And Fixing Of GI Slotted Cable Tray 100 X 50mm High In 16 SWG Incl Necessary Supports And Frame Work Complete All As Specified And As Directed By Engineer In ChargeQuantity20Delivery90 daysDetailsClose
Delivery
90 days
17Supply And Fixing Of 4 Mm GI WireQuantity25Delivery90 daysDetailsClose
Delivery
90 days
18Supply Laying And Testing PVC Ensu Lated PVC Sheathed Cable Galvanized Steel Strip Or Wire Armoured Electric Control Cables Heavy Duty With Stranded Copper Conductor As Per ATCQuantity50Delivery90 daysDetailsClose
Delivery
90 days
19Supply Install Commissioning And Testing Of Air Cooled Packaged Air Conditioners Comprising Of Hermetic Or Semi Hermetically Sealed Reciprocating Or Hermetically As Per ATCQuantity9Delivery90 daysDetailsClose
Delivery
90 days
20M And L For Taking Out Old BER AC 3 Or 4 Or 7 Point 5 TR Ton Capacities Complete And Transporting Them To AGE EM Store Yard And Deposit Complete All As Specified And DirectedQuantity11Delivery90 daysDetailsClose
Delivery
90 days

Tender documents

Bid files and supporting documents, linked directly from GeM.

Policy & contract references

Documents you must submit

  • Experience Criteria
  • Past Performance
  • Bidder Turnover
  • Certificate (Requested in ATC)
  • OEM Authorization Certificate
  • OEM Annual Turnover

Eligibility

From the bid and reverse-auction documents

Experience

3 years

Min. turnover

₹12 L

a year, 3-year average

OEM turnover

₹12 L

Past performance

80%

of the bid quantity

Experience & turnover exemptions

Micro & small enterprises (MSE)

Complete exemption
From the reverse auction
Exemption conditions

Yes | Complete

View PDF · p. 2

Startups

Complete exemption
From the reverse auction
Exemption conditions

Yes | Complete

View PDF · p. 2

Exemptions depend on the evidence and conditions specified in the bid.

Preferences & relaxations

From the bid document

  • MSE purchase preference
  • MII preference
  • Class-1/2 local suppliers
  • EMD exemption: no
  • Inspection required: no

Check each criterion against the tender notice before you bid.

Commercial conditions

From the bid document

EMD
₹90,000
Performance guarantee
3% for 14 months
Offer validity
90 days

Reverse auction extension

From the reverse auction

If any seller submits the offer price during last 15 minutes of RA end time, then RA will be automatically extended for next 15 minutes from the last participation time. There is no limit on such RA extension cycle.

View PDF · p. 2

Buyer requirements & conditions

Buyer-added conditions from the bid and the reverse-auction documents.

From the bid document

OPTION CLAUSE: The Purchaser reserves the right to increase or decrease the quantity to be ordered up to 25 percent of bid quantity at the time of placement of contract. The purchaser also reserves the right to increase the ordered quantity up to 25% of the contracted quantity during the currency of the contract at the contracted rates. The delivery period of quantity shall commence from the last date of original delivery order and in cases where option clause is exercised during the extended delivery period the additional time shall commence from the last date of extended delivery period. The additional delivery time shall be (Increased quantity ÷ Original quantity) × Original delivery period (in days), subject to minimum of 30 days. If the original delivery period is less than 30 days, the additional time equals the original delivery period. The Purchaser may extend this calculated delivery duration up to the original delivery period while exercising the option clause. Bidders must comply with these terms.

02

Certificates

View PDF · p. 17

Bidder's offer is liable to be rejected if they don't upload any of the certificates / documents sought in the Bid document, ATC and Corrigendum if any.

Bidder shall submit the following documents along with their bid for Vendor Code Creation:

  • a.Copy of PAN Card.
  • b.Copy of GSTIN.
  • c.Copy of Cancelled Cheque.
  • d.Copy of EFT Mandate duly certified by Bank.
04

Buyer Added Bid Specific ATC

View PDF · p. 18

Buyer uploaded ATC document Click here to view the file.

From the reverse auction

Reverse auction — offer validity

View PDF · p. 3

Participation by the bidder in RA process would be considered as their consent for extension in offer validity by 30 days by the date of RA initiation.

Similar open tenders

Soonest first

Search similar in the explorerFind this tender in the explorer

Open on GeM